(Tuesday, Nov 20 at 08:45)
m (Wednesday, Nov 20 at 08:45)
 
(8 intermediate revisions by 2 users not shown)
Line 14: Line 14:
 
*[https://halldweb.jlab.org/wiki/index.php/File:Fall18_week9.jpg Hall D schedule for week 9]
 
*[https://halldweb.jlab.org/wiki/index.php/File:Fall18_week9.jpg Hall D schedule for week 9]
 
*[https://halldweb.jlab.org/wiki/images/9/90/Fall18_week10.jpg Hall D schedule for week 10]
 
*[https://halldweb.jlab.org/wiki/images/9/90/Fall18_week10.jpg Hall D schedule for week 10]
 +
 +
 +
 +
== Wednesday, Nov 21 at 08:45 ==
 +
 +
#Last 24h:
 +
#* Baseline calibration: Sergei, Beni.
 +
#* Luminosity studies
 +
#* Harp Scan [http://zeus.phys.uconn.edu/halld/cobrems/harptool.cgi?harp5C11_xsigma=1.535&harp5C11_xsigma_err=0.04&harp5C11_ysigma=1.221&harp5C11_ysigma_err=0.04&harp5C11B_xsigma=1.456&harp5C11B_xsigma_err=0.04&harp5C11B_ysigma=0.916&harp5C11B_ysigma_err=0.04&radHarp_xsigma=1.388&radHarp_xsigma_err=0.2&radHarp_ysigma=0.7697&radHarp_ysigma_err=0.2&harp5C11_spos=102.97&harp5C11B_spos=115.11&emittance_x=0.0062&radHarp_spos=119.7&emittance_y=0.0044&collimator_spos=194.92&fit=fit+and+plot]
 +
#Issues
 +
#* [https://logbooks.jlab.org/entry/3629008 tagger magnetic field] Hovanes
 +
#Reports
 +
#* [https://logbooks.jlab.org/entry/3628918 DCs status during luminosity studies] Lubomir, Beni.
 +
#* [https://logbooks.jlab.org/entry/3629292 Rates during luminosity study] (Alexandre D.)
 +
#* [https://logbooks.jlab.org/entry/3629317 Monitoring report] (Thomas)
 +
#Plans
 +
#* [https://halldweb.jlab.org/wiki/images/8/84/Fall18_week9.jpg Time chart for last week]
 +
#* [https://halldweb.jlab.org/wiki/index.php/File:Fall18_week10.jpg Time chart for this week]
 +
#* Luminosity study.
 +
#* Harp Scan
 +
#Discussion ComCal commissioning
 +
#* [https://halldweb.jlab.org/wiki/index.php/File:Run_Plan_Fall_2018-v3c.jpg Latest runplan (V.3c) ]
 +
#* Time chart, updated after 11/15/2018 discussion
 +
#** [https://halldweb.jlab.org/wiki/images/c/ca/Fall18_week11.jpg Week 11]
 +
#**  [https://halldweb.jlab.org/wiki/images/8/8b/Fall18_week12.jpg Week 12]
 +
#** [https://halldweb.jlab.org/wiki/images/5/50/Fall18_week13.jpg Week 13]
 +
#Notes
  
 
== Tuesday, Nov 20 at 08:45 ==
 
== Tuesday, Nov 20 at 08:45 ==
Line 28: Line 55:
 
#Plans
 
#Plans
 
#* [https://halldweb.jlab.org/wiki/images/8/84/Fall18_week9.jpg Time chart for this week]
 
#* [https://halldweb.jlab.org/wiki/images/8/84/Fall18_week9.jpg Time chart for this week]
#*<font color="red"><b>[https://docs.google.com/spreadsheets/d/1UT3o4yJ-avlIQzmZKJo2nRrgVPzYKJvGPJ0oqAn81Oo/edit?usp=sharing Luminosity study] </b></font>J. Stevens
+
#*<font color="red"><b>Luminosity study. [https://docs.google.com/spreadsheets/d/1UT3o4yJ-avlIQzmZKJo2nRrgVPzYKJvGPJ0oqAn81Oo/edit?usp=sharing Plan] </b></font>J. Stevens
 
#* Standard production running
 
#* Standard production running
 
#Discussion ComCal commissioning
 
#Discussion ComCal commissioning

Latest revision as of 05:07, 22 November 2018

<- Back to Run Coordination Meetings:Fall2018 Run



Wednesday, Nov 21 at 08:45

  1. Last 24h:
    • Baseline calibration: Sergei, Beni.
    • Luminosity studies
    • Harp Scan [1]
  2. Issues
  3. Reports
  4. Plans
  5. Discussion ComCal commissioning
  6. Notes

Tuesday, Nov 20 at 08:45

  1. Last 24h:
    • FCal HV scan (A. Somov)
    • 2pm-6pm: optic optimization (T. Satogata)
    • Standard production running
  2. Issues
    • Optic tuning unsuccessful: background on our Harp scan 100 times larger and some of the tagger radiation monitors have twice larger signals. Scrapping is likely the cause. MCC backed-out of the new optics. Harp background and radiation monitor signals back to normal. Transmission back to the same as Monday morning (still 15% lower than at the start of the month).
    • Coherent peak shape (Beni)
  3. Reports
  4. Plans
  5. Discussion ComCal commissioning
  6. Notes

Monday, Nov 19 at 08:45

  1. Last 72h:
    • Friday Morning: Optic optimization
    • TAC run (Alexander S.)
    • Empty target run+ raw mode run
    • Standard production running
  2. Issues
  3. Reports
  4. Plans
    • Time chart for this week
    • 30 min FCal scan (A. Somov)
    • 2pm: optic optimization (T. Satogata)
    • Standard production running
  5. Discussion ComCal commissioning
  6. Notes

Friday, Nov 16 at 08:45

  1. Last 24h:
    • Check V-wire rate in preparation for TAC on Friday. (Alexander S.)
    • Check issue with CBrem gui. It appears to be gone (Hovanes)
    • Maintenance: 1pm-4/5pm.
    • Standard production running
  2. Issues
  3. Reports
  4. Plans
    • Time chart for this week
    • Optics adjustment (Todd/Jay) 30 min.
    • TAC run this morning/afternoon.
    • Standard production running over the week end.
  5. Discussion ComCal commissioning
  6. Notes
    • No meetings this week end.

Thursday, Nov 15 at 08:45

  1. Last 24h:
    • Standard production running
  2. Issues
  3. Reports
  4. Plans
    • Monday maintenance is moved to today, 1pm-4/5pm.
    • Check V-wire position wrt beam (Sacha).
    • Investigate issue with CBrem gui. Meanwhile, fill the target.
    • Production running, starting with amorphous (for CBrem ref.)
    • Optics adjustment (Todd/Jay) 30 min.
      • Access to move back the flux monitor
      • Other access?
    • TAC run this morning/afternoon is postponed.
    • Optics adjustment (Todd/Jay) 30 min.
  5. Discussion ComCal commissioning
  6. Notes