Difference between revisions of "Run Planning Meeting Notes, Nov 21-Nov 28, 2018"
From GlueXWiki
(Created page with "<- Back to Run Coordination Meetings:Fall2018 Run * [https://halldweb.jlab.org/data_monitoring/run_statistics/RunPeriod-2018-08/index.html Trigger graphs] * [https://docs...") |
|||
Line 17: | Line 17: | ||
== Friday, Nov 23 at 10:00 == | == Friday, Nov 23 at 10:00 == | ||
* Its Black Friday! | * Its Black Friday! | ||
− | * | + | |
− | * Continue with data production | + | # Since Wednesday |
+ | #* Start with luminosity scan. | ||
+ | #* First part complete: Amo and Diamond up to 300nA beam, Mode 9 and 10(raw) | ||
+ | #* Continue with data production | ||
+ | #* Thursday early morning, major beam down due to communication failure to RF chassis (pc104 cpu). | ||
+ | #* Major power glitch "Brown out", caused down on Friday early morning. |
Revision as of 09:36, 23 November 2018
<- Back to Run Coordination Meetings:Fall2018 Run
- Trigger graphs
- Trigger Spreadsheet
- Low energy running Trigger Spreadsheet
- Run Plan Google Calendar
- Accel. Plan Google Calendar
- Acc whiteboard
- Counting house whiteboard
- Hall D schedule for week 8
- Hall D schedule for week 9
Friday, Nov 23 at 10:00
- Its Black Friday!
- Since Wednesday
- Start with luminosity scan.
- First part complete: Amo and Diamond up to 300nA beam, Mode 9 and 10(raw)
- Continue with data production
- Thursday early morning, major beam down due to communication failure to RF chassis (pc104 cpu).
- Major power glitch "Brown out", caused down on Friday early morning.