Difference between revisions of "Run Planning Meeting Notes, Nov 29-Dec 6, 2018"

From GlueXWiki
Jump to: navigation, search
(Wednesday, Nov 28 at 8:45)
(Wednesday, Nov 28 at 8:45)
Line 5: Line 5:
 
#* Completed at 6pm yesterday
 
#* Completed at 6pm yesterday
 
#  First sight of beam (by Comp Cal)
 
#  First sight of beam (by Comp Cal)
Swing and Overnight Running
+
# Swing and Overnight Running
#* 15 nA on Al V-wire.
+
#* 15 nA on Al V-wire [https://logbooks.jlab.org/entry/3633248 running condition].
 
#* Lost beam around 2pm (due to radiation damaged valve position sensor).
 
#* Lost beam around 2pm (due to radiation damaged valve position sensor).
 
# FCAL is down:
 
# FCAL is down:
 
#* Rapid access is arrange between 10am - noon.
 
#* Rapid access is arrange between 10am - noon.
 
# Run Plan:
 
# Run Plan:
#* [https://halldweb.jlab.org/wiki/images/c/ca/Fall18_week13.jpg Week13]
+
#*
#* Second Energy change will take about 48 hours
+

Revision as of 09:29, 30 November 2018

Wednesday, Nov 28 at 8:45

  1. Cryo
    • solenoid helium fill test this morning
  2. Comp Cal installation
    • Completed at 6pm yesterday
  3. First sight of beam (by Comp Cal)
  4. Swing and Overnight Running
    • 15 nA on Al V-wire running condition.
    • Lost beam around 2pm (due to radiation damaged valve position sensor).
  5. FCAL is down:
    • Rapid access is arrange between 10am - noon.
  6. Run Plan: