Difference between revisions of "Run Planning Meeting Notes, Nov 29-Dec 6, 2018"

From GlueXWiki
Jump to: navigation, search
(Wednesday, Nov 28 at 8:45)
(Friday, Nov 30 at 8:45)
 
(5 intermediate revisions by the same user not shown)
Line 1: Line 1:
== Wednesday, Nov 28 at 8:45 ==
+
 
# Comp Cal installation
+
#* Completed at 6pm yesterday
+
#  First sight of beam (by Comp Cal): https://logbooks.jlab.org/entry/3633247
+
# Swing and Overnight Running
+
#* 15 nA on Al V-wire ([https://logbooks.jlab.org/entry/3633248 full running condition]).
+
#* Lost beam around 2pm (due to radiation damaged valve position sensor).
+
# FCAL is down:
+
#* [Monitoring current draw on CAN bus https://logbooks.jlab.org/entry/3633312] [Matt]
+
#* Rapid access is arrange between 10am - noon.
+
# Run Plan:
+
#*
+
# Cryo
+
#* solenoid helium fill test this morning
+

Latest revision as of 00:46, 3 December 2018