Difference between revisions of "Run Planning Meeting Notes, Nov 8-Nov 14, 2018"

From GlueXWiki
Jump to: navigation, search
(Thursday, Nov 8 at 08:45)
(Thursday, Nov 8 at 08:45)
Line 16: Line 16:
 
#* Beam tuning (deferred)
 
#* Beam tuning (deferred)
 
#* Data taking with reduced PS field, coherent edge at 7GeV
 
#* Data taking with reduced PS field, coherent edge at 7GeV
#** [Rates https://logbooks.jlab.org/entry/3622899]
+
#** [https://logbooks.jlab.org/entry/3622899 Rates]
 
#** Low energy running [https://docs.google.com/spreadsheets/d/1qJv80NKS1zCrBj5utogCAIBo5KZXtTocV0fc5pqfx_0/edit?usp=sharing Trigger Spreadsheet]
 
#** Low energy running [https://docs.google.com/spreadsheets/d/1qJv80NKS1zCrBj5utogCAIBo5KZXtTocV0fc5pqfx_0/edit?usp=sharing Trigger Spreadsheet]
 
#Issues
 
#Issues

Revision as of 09:33, 8 November 2018

<- Back to Run Coordination Meetings:Fall2018 Run

Thursday, Nov 8 at 08:45

  1. Last 24h:
  2. Issues
    • PS and PSC coincidence scalers frozen, ps_client running on gluon100 restarted, instructions in hdops wiki
    • beam position went awry, rates soared, reference module for IOC reading out 5C11B failed, replaced
    • EPICS froze for 2h, started working without intervention
  3. Reports
    • Monitoring
  4. Plans
  5. Notes