Difference between revisions of "Run Planning Meeting Notes, November 11 - November 17, 2021"
From GlueXWiki
(→Thursday November 11) |
|||
Line 1: | Line 1: | ||
+ | =Monday November 15= | ||
+ | #Last 72h: | ||
+ | #* recorded 5.6B+ triggers on diamond and 140M on AMO (starting 17:30 on Friday) | ||
+ | #* after the [https://logbooks.jlab.org/entry/3941683 colimator scan] (Fri 13:30-16:30) restored old quad settings (10% transmission increase). | ||
+ | #* writing on tape stopped Saturday morning (disks can take up to 3 days running) | ||
+ | #* higher than normal trip rate Saturday/Sunday | ||
+ | #Issues: | ||
+ | #* writing on tape | ||
+ | # [https://halldweb.jlab.org/wiki/index.php/SRC/CT_Run_Plan Plan:] | ||
+ | #* expect no/bad beam day shift (RF working on cavities) | ||
+ | #* BCM calibration for Hall C energy measurements 14:30-15:30 | ||
+ | #* Continue production at 150nA on diamond | ||
+ | #* plan for target changes | ||
+ | # Analysis update | ||
+ | |||
=Friday November 12= | =Friday November 12= | ||
#Last 24h: | #Last 24h: |
Revision as of 23:51, 14 November 2021
Monday November 15
- Last 72h:
- recorded 5.6B+ triggers on diamond and 140M on AMO (starting 17:30 on Friday)
- after the colimator scan (Fri 13:30-16:30) restored old quad settings (10% transmission increase).
- writing on tape stopped Saturday morning (disks can take up to 3 days running)
- higher than normal trip rate Saturday/Sunday
- Issues:
- writing on tape
- Plan:
- expect no/bad beam day shift (RF working on cavities)
- BCM calibration for Hall C energy measurements 14:30-15:30
- Continue production at 150nA on diamond
- plan for target changes
- Analysis update
Friday November 12
- Last 24h:
- Issues:
- bad f250 in TAGH [6] - no longer an issue (Sasha power-cycled the crate)
- transmission - Hovanes will do AC scan when the beam is back after 10am - profiler doesn't lock has to be fixed at that time, as well
- Plan:
- Down starting at 10am: for 1+ hours (Hall A changes to 4 passes) - FCAL items will be surveyed
- Continue production at 150nA on diamond
- Analysis update