Run Planning Meeting Notes, November 18 - November 24, 2021

From GlueXWiki
Revision as of 20:31, 18 November 2021 by Staylor (Talk | contribs)

Jump to: navigation, search

Friday, November 19

  1. Last 24h:
  • XXX B triggers: [1]
  1. Issues:
  1. Plan:
    • Continue production at 150nA on diamond
  2. Analysis update


Thursday November 18

  1. Last 24h:
    • ~1.4 B triggers (250M AMO): [2]
    • Down from ~8:45 am -> 9:30 pm due to 4th pass RF separator problem
      • Repair plan: down at ~10 am for ~30 minutes, then acc will decide if full system needs to be down for repair for longer time
      • Some discussion regarding using magnetic separation for 1 hall running if down more than 30 minutes
  2. Issues:
    • writing on tape?
    • High temperature of locked-up FCAL bases? [3]
    • Shift crew will take over servicing FCAL base lock ups. wiki instructions
  3. Plan:
    • Continue production at 150nA on diamond
  4. Analysis update