Difference between revisions of "Run Planning Meeting Notes, November 4 - November 10, 2021"

From GlueXWiki
Jump to: navigation, search
(Thursday November 04)
(Thursday November 04)
Line 17: Line 17:
 
#** RadCon survey for Friday morning is requested
 
#** RadCon survey for Friday morning is requested
 
#** Safety Walkthrough scheduled for Friday 2pm
 
#** Safety Walkthrough scheduled for Friday 2pm
 +
#** EEL Closure from November 5th, 6pm to November 8th, 6am and November 12th, 6pm to November 15th, 6am

Revision as of 14:42, 3 November 2021

MCC whiteboard Meeting Bluejeans 660743227 Trigger Counter

Thursday November 04

  1. Last 24h:
    • Maintenance day
    • Replaced FCAL 15 bases [1]
    • Restored beam at X:XXpm
    • Harp scan
    • Recorded XXXM+ events with full LHe4 target
  2. Issues:
  3. Plan:
    • Continue production at 200nA with the solenoid on after that.
    • MCC (Jay) discussed possibility to move up the energy shift to Thu, swing
      • Controlled access planned for maintenance work (e.g. FCAL [2])
    • Beam energy change planned for 11/05-11/07
      • RadCon survey for Friday morning is requested
      • Safety Walkthrough scheduled for Friday 2pm
      • EEL Closure from November 5th, 6pm to November 8th, 6am and November 12th, 6pm to November 15th, 6am