Difference between revisions of "Run Planning Meeting Notes, November 4 - November 10, 2021"

From GlueXWiki
Jump to: navigation, search
(Friday November 05)
(Friday November 05)
Line 5: Line 5:
 
#Last 24h:
 
#Last 24h:
 
#* 7h accelerator down time due to power outage [https://logbooks.jlab.org/entry/3937004]
 
#* 7h accelerator down time due to power outage [https://logbooks.jlab.org/entry/3937004]
 +
#* New modules installed in FCal2 test stand [https://logbooks.jlab.org/entry/3937087] (Sasha)
 
#* Beam restored around 2pm
 
#* Beam restored around 2pm
 
#* Trigger studies with 20nA and 100nA (Sasha)
 
#* Trigger studies with 20nA and 100nA (Sasha)

Revision as of 07:40, 5 November 2021

MCC whiteboard Meeting Bluejeans 660743227 Trigger Counter

Friday November 05

  1. Last 24h:
    • 7h accelerator down time due to power outage [1]
    • New modules installed in FCal2 test stand [2] (Sasha)
    • Beam restored around 2pm
    • Trigger studies with 20nA and 100nA (Sasha)
    • Recorded 800M+ events with full lHe4 target
    • 8am: PrimEx EoR
  2. Issues:
  3. Plan:
    • Beam energy change 11/05-11/07, start Friday 8am
      • Cancel shifts from Friday 10am?
      • RadCon survey for tagger halld done at 8am, leave hall and tagger in controlled
      • Safety Walkthrough scheduled for Friday 2pm (Elton)
      • Installation of Youri's detector near the PS on Sunday, calorimeter test has to go today?
      • Maintenance of the A/C for the server room: shut off for more than 10min, ramp down servers?
    • Start SRC/CT experiment on Monday
      • Wiki page
      • Morning meeting at same time, but new number: 497773790/1473
      • Do we want to start a new run period 2021-11?
      • Continue SRC/CT run plan discussion here

Thursday November 04

  1. Last 24h:
    • Maintenance day
    • Replaced FCAL 15 bases [3]
    • Restored beam at 11:00pm
    • Harp scan [4]
    • Recorded 150M+ events with full LHe4 target
    • Several beam interruptions, currently loss of power, might take a few hours to restore
  2. Issues:
    • CDC HV alarm at 2:45am, restored by itself for all but one channel (F:14), but HV OK, acknowledged
    • BCAL LED trigger script was off for runs 81702 and 82703. Switched on afterwards.
  3. Plan:
    • Continue production at 200nA with the solenoid on
    • Beam energy change planned for 11/05-11/07, start Friday ~7am
      • Cancel shifts from Friday 10am?
      • RadCon survey for Friday morning is requested, leave hall in controlled, only survey tagger hall?
      • Safety Walkthrough scheduled for Friday 2pm (Elton)
      • EEL Closure from November 5th, 6pm to November 8th, 6am and November 12th, 6pm to November 15th, 6am