Run Planning Meeting Notes, November 4 - November 10, 2021

From GlueXWiki
Revision as of 10:53, 3 November 2021 by Aaustreg (Talk | contribs) (Created page with "[https://cebaf.jlab.org/files/ops/accboard/ MCC whiteboard] [https://bluejeans.com/660743227 Meeting Bluejeans 660743227] [https://halldweb.jlab.org/data_monitoring/run_statis...")

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search

MCC whiteboard Meeting Bluejeans 660743227 Trigger Counter

Thursday November 04

  1. Last 24h:
    • Maintenance day
    • Recorded XXXM+ events with full LHe4 target
  2. Issues:
  3. Plan:
    • Continue production at 200nA with the solenoid on after that.
    • MCC (Jay) discussed possibility to move up the energy shift to Thu, swing
      • Controlled access planned for maintenance work (e.g. FCAL [1])
    • Beam energy change planned for 11/05-11/07
      • RadCon survey for Friday morning is requested
      • Safety Walkthrough scheduled for Friday 2pm