Difference between revisions of "Run Planning Meeting Notes, Oct 11-Oct 17, 2018"

From GlueXWiki
Jump to: navigation, search
Line 1: Line 1:
 
== Thursday, Oct 11 at 08:45 ==
 
== Thursday, Oct 11 at 08:45 ==
 
# Notes from the past 24 hours:
 
# Notes from the past 24 hours:
#* Beam issues most of swing (7hrs to do amorphous run) and owl shift.
+
#* Beam issues most of swing (7hrs to complete amorphous run) and owl shift (~1hr of beam in total).
 
+
 
#CEBAF
 
#CEBAF
 
#* 5th pass separator failed during swing shift and into the beginning of owl. Beam back at 3:20am.
 
#* 5th pass separator failed during swing shift and into the beginning of owl. Beam back at 3:20am.
Line 11: Line 10:
 
#* [https://logbooks.jlab.org/entry/3607600 Lots of issues with DAQ- rocCDC2]
 
#* [https://logbooks.jlab.org/entry/3607600 Lots of issues with DAQ- rocCDC2]
 
#Reports
 
#Reports
#*[ Monitoring Report]
+
#*[https://logbooks.jlab.org/entry/3607590 Monitoring Report]
 
#* [https://halldweb.jlab.org/data_monitoring/Plot_Browser.html Plot Browser]  
 
#* [https://halldweb.jlab.org/data_monitoring/Plot_Browser.html Plot Browser]  
 
#*[https://logbooks.jlab.org/entry/3607032 Rate and Energy Monitoring]
 
#*[https://logbooks.jlab.org/entry/3607032 Rate and Energy Monitoring]

Revision as of 08:27, 11 October 2018

Thursday, Oct 11 at 08:45

  1. Notes from the past 24 hours:
    • Beam issues most of swing (7hrs to complete amorphous run) and owl shift (~1hr of beam in total).
  2. CEBAF
    • 5th pass separator failed during swing shift and into the beginning of owl. Beam back at 3:20am.
    • PSS drop in the machine at 3:30 am. No beam until 6am.
  3. Action Items
  4. Issues
  5. Reports
  6. Run Plan
    • Need to schedule a TAC run
      • Can we do this opportunistically?
      • Use bleedthrough current?
      • Hall C plans to switch experiments on approximately the 22nd. This is around the time of accelerator maintenance, so they may plan to switch experiments then.
    • Hurricane Michael closely approaching. Do we need to take any precautions?
    • Week 4 Week 5
      • Beam Studies Monday
      • RF Recovery Monday
  7. AOB