Difference between revisions of "Run Planning Meeting Notes, Oct 11-Oct 17, 2018"

From GlueXWiki
Jump to: navigation, search
(Thursday, Oct 11 at 08:45)
Line 22: Line 22:
 
#* [https://halldweb.jlab.org/wiki/images/d/de/Fall18_week4.jpg Week 4] [https://halldweb.jlab.org/wiki/index.php/File:Fall18_week5.jpg Week 5]
 
#* [https://halldweb.jlab.org/wiki/images/d/de/Fall18_week4.jpg Week 4] [https://halldweb.jlab.org/wiki/index.php/File:Fall18_week5.jpg Week 5]
 
#**Beam Studies Monday
 
#**Beam Studies Monday
#**RF Recovery Monday
+
#**RF Recovery Tuesday
 
#*
 
#*
 
#AOB
 
#AOB

Revision as of 08:33, 11 October 2018

Thursday, Oct 11 at 08:45

  1. Notes from the past 24 hours:
    • Beam issues most of swing (7hrs to complete amorphous run) and owl shift (~1hr of beam in total).
  2. CEBAF
    • 5th pass separator failed during swing shift and remained problematic into the beginning of owl. Beam back at 3:20am.
    • PSS drop in the machine at 3:30 am. No beam until 6am.
  3. Action Items
  4. Issues
  5. Reports
  6. Run Plan
    • Need to schedule a TAC run
      • Can we do this opportunistically?
      • Use bleedthrough current?
      • Hall C plans to switch experiments on approximately the 22nd. This is around the time of accelerator maintenance, so they may plan to switch experiments then.
    • Hurricane Michael closely approaching. Do we need to take any precautions?
    • Week 4 Week 5
      • Beam Studies Monday
      • RF Recovery Tuesday
  7. AOB