(Thursday, Oct 11 at 08:45)
Line 19: Line 19:
 
#Run Plan
 
#Run Plan
 
#* Hurricane Michael closely approaching. Do we need to take any precautions?
 
#* Hurricane Michael closely approaching. Do we need to take any precautions?
#* [https://halldweb.jlab.org/wiki/images/4/49/Fall18_week3.jpg Week 3] [https://halldweb.jlab.org/wiki/images/d/de/Fall18_week4.jpg Week 4]
+
#* [https://halldweb.jlab.org/wiki/images/d/de/Fall18_week4.jpg Week 4] [https://halldweb.jlab.org/wiki/index.php/File:Fall18_week5.jpg Week 5]
 
#**Beam Studies Monday
 
#**Beam Studies Monday
 
#**RF Recovery Monday
 
#**RF Recovery Monday
 
#*
 
#*
 
#AOB
 
#AOB

Revision as of 08:21, 11 October 2018

Thursday, Oct 11 at 08:45

  1. Notes from the past 24 hours:
    • Beam issues most of swing (7hrs to do amorphous run) and owl shift.
  1. CEBAF
    • 5th pass separator failed during swing shift and into the beginning of owl. Beam back at 3:20am.
    • PSS drop in the machine at 3:30 am. No beam until 6am.
  2. Action Items
  3. Issues
    • Need to schedule a TAC run
      • Can we do this opportunistically?
      • Use bleedthrough current?
      • Hall C plans to switch experiments on approximately the 22nd. This is around the time of accelerator maintenance, so they may plan to switch experiments then.
    • MyaViewer missing events
  4. Reports
  5. Run Plan
    • Hurricane Michael closely approaching. Do we need to take any precautions?
    • Week 4 Week 5
      • Beam Studies Monday
      • RF Recovery Monday
  6. AOB