Run Planning Meeting Notes, Oct 11-Oct 17, 2018

From GlueXWiki
Revision as of 07:14, 11 October 2018 by Gleasonc (Talk | contribs) (Thursday, Oct 11 at 08:45)

Jump to: navigation, search

Thursday, Oct 11 at 08:45

  1. Notes from the past 24 hours:
    • Beam issues most of swing (7hrs to do amorphous run) and owl shift.
  2. CEBAF
    • 5th pass separator failed during swing shift and into the beginning of owl. Beam back at 3:20am.
    • PSS drop in the machine at 3:30 am. No beam until 6am.
  3. Action Items
  4. Issues
  5. Reports
  6. Run Plan
    • Hurricane Michael closely approaching. Do we need to take any precautions?
    • Week 3 Week 4
      • Beam Studies Monday
      • RF Recovery Monday
  7. AOB