(Thursday, Oct 18 at 08:45)
Line 1: Line 1:
 +
== Friday, Oct 19 at 08:45 ==
 +
# Notes from the past 24 hours:
 +
#* Alignment of JD70-105 47um in 10 hours. THANKS TO HOVANES!
 +
#** [https://logbooks.jlab.org/entry/3611673]
 +
#* Amo run taken
 +
#* Harp scan taken: same beam conditions as on Wednesday evening
 +
#* PARA and PERP at 0/90 with new diamond in the books!
 +
#* [https://logbooks.jlab.org/entry/3611763 Beam last 24h]
 +
# Report:
 +
#* [https://logbooks.jlab.org/entry/3611752 Frequent drop of beam energy measurement]
 +
#* [https://logbooks.jlab.org/entry/3611794 Data Rates on New Diamond]
 +
#* [https://logbooks.jlab.org/entry/3611784 Data Monitoring]
 +
# Actions Required:
 +
#* TAKE DATA!
 +
# Weekly Beam forecast: [https://cebaf.jlab.org/files/ops/accboard/ CEBAF-WhiteBoard]
 +
#* HallA machine development (Tue.-Wed) may shift to Mon.-Tue.!
 +
# Run Plan:
 +
#* Run with no radiator at high current (Lubomir)
 +
#** Raw mode, LED (FP) trigger to 5kHz!
 +
#* [https://halldweb.jlab.org/wiki/images/d/de/Fall18_week4.jpg Week 4]
 +
#* [https://halldweb.jlab.org/wiki/index.php/File:Fall18_week5.jpg Week 5]
 +
#* [https://halldweb.jlab.org/wiki/index.php/File:Fall18_week6.jpg Week 6]
 +
 +
 
== Thursday, Oct 18 at 08:45 ==
 
== Thursday, Oct 18 at 08:45 ==
 
# Notes from the past 24 hours:
 
# Notes from the past 24 hours:

Revision as of 08:31, 19 October 2018

Friday, Oct 19 at 08:45

  1. Notes from the past 24 hours:
    • Alignment of JD70-105 47um in 10 hours. THANKS TO HOVANES!
    • Amo run taken
    • Harp scan taken: same beam conditions as on Wednesday evening
    • PARA and PERP at 0/90 with new diamond in the books!
    • Beam last 24h
  2. Report:
  3. Actions Required:
    • TAKE DATA!
  4. Weekly Beam forecast: CEBAF-WhiteBoard
    • HallA machine development (Tue.-Wed) may shift to Mon.-Tue.!
  5. Run Plan:
    • Run with no radiator at high current (Lubomir)
      • Raw mode, LED (FP) trigger to 5kHz!
    • Week 4
    • Week 5
    • Week 6


Thursday, Oct 18 at 08:45

  1. Notes from the past 24 hours:
  2. Actions Required:
    • photon beam, coherent peak!
    • need good beam AND diamond for the week end!
  3. Weekly Beam forecast: CEBAF-WhiteBoard
    • Beam studies Monday, HallC 4hour access
    • RF recovery Tuesday, HallC aerogel installation
    • Wednesday 7am(?) to Thursday midnight Hall-A beam tune. No beam or only parasitic other halls.
      • take advantage of down for installations?
    • TAC postpone to Friday 10/26?????
  4. Reports:
  5. Run Plan