== Monday, Oct 22 at 08:45 ==
 +
# This past week end
 +
#* quite smooth running: [https://logbooks.jlab.org/entry/3612992 beam over the week end]
 +
#* Friday beam tune by Todd: [https://logbooks.jlab.org/entry/3611925 elog entry]
 +
# Issues over the week end
 +
#* DAQ, gluon04, No PS-trigger on display (DAQ-trigger ok!)
 +
#* [https://logbooks.jlab.org/entry/3613012 Data Monitoring]
 +
#* [https://logbooks.jlab.org/entry/3613021 FCAL performance]
 +
#* beam intensity issues this morning 7am .... Moday morning start of the work day
 +
# Today:
 +
#* Safety walk through
 +
#* [https://logbooks.jlab.org/entry/3613003 Tagger beam line vacuum]
 +
 +
 
== Friday, Oct 19 at 08:45 ==
 
== Friday, Oct 19 at 08:45 ==
 
# Notes from the past 24 hours:
 
# Notes from the past 24 hours:

Revision as of 08:35, 22 October 2018

Monday, Oct 22 at 08:45

  1. This past week end
  2. Issues over the week end
    • DAQ, gluon04, No PS-trigger on display (DAQ-trigger ok!)
    • Data Monitoring
    • FCAL performance
    • beam intensity issues this morning 7am .... Moday morning start of the work day
  3. Today:


Friday, Oct 19 at 08:45

  1. Notes from the past 24 hours:
    • Alignment of JD70-105 47um in 10 hours. THANKS TO HOVANES!
    • Amo run taken
    • Harp scan taken: same beam conditions as on Wednesday evening
    • PARA and PERP at 0/90 with new diamond in the books!
    • Beam last 24h
  2. Report:
  3. Actions Required:
    • TAKE DATA!
  4. Weekly Beam forecast: CEBAF-WhiteBoard
    • HallA machine development (Tue.-Wed) may shift to Mon.-Tue.!
  5. Run Plan:
    • Run with no radiator at high current (Lubomir)
      • Raw mode, LED (FP) trigger to 5kHz!
    • Week 5
    • Week 6
  6. WTFATRC
    • NEED RC in 2 weeks!
  7. ANY other business

Thursday, Oct 18 at 08:45

  1. Notes from the past 24 hours:
  2. Actions Required:
    • photon beam, coherent peak!
    • need good beam AND diamond for the week end!
  3. Weekly Beam forecast: CEBAF-WhiteBoard
    • Beam studies Monday, HallC 4hour access
    • RF recovery Tuesday, HallC aerogel installation
    • Wednesday 7am(?) to Thursday midnight Hall-A beam tune. No beam or only parasitic other halls.
      • take advantage of down for installations?
    • TAC postpone to Friday 10/26?????
  4. Reports:
  5. Run Plan