Difference between revisions of "Run Planning Meeting Notes, Oct 18-Oct 24, 2018"
From GlueXWiki
(→Friday, Oct 19 at 08:45) |
|||
Line 1: | Line 1: | ||
+ | == Monday, Oct 22 at 08:45 == | ||
+ | # This past week end | ||
+ | #* quite smooth running: [https://logbooks.jlab.org/entry/3612992 beam over the week end] | ||
+ | #* Friday beam tune by Todd: [https://logbooks.jlab.org/entry/3611925 elog entry] | ||
+ | # Issues over the week end | ||
+ | #* DAQ, gluon04, No PS-trigger on display (DAQ-trigger ok!) | ||
+ | #* [https://logbooks.jlab.org/entry/3613012 Data Monitoring] | ||
+ | #* [https://logbooks.jlab.org/entry/3613021 FCAL performance] | ||
+ | #* beam intensity issues this morning 7am .... Moday morning start of the work day | ||
+ | # Today: | ||
+ | #* Safety walk through | ||
+ | #* [https://logbooks.jlab.org/entry/3613003 Tagger beam line vacuum] | ||
+ | |||
+ | |||
== Friday, Oct 19 at 08:45 == | == Friday, Oct 19 at 08:45 == | ||
# Notes from the past 24 hours: | # Notes from the past 24 hours: |
Revision as of 08:35, 22 October 2018
Monday, Oct 22 at 08:45
- This past week end
- quite smooth running: beam over the week end
- Friday beam tune by Todd: elog entry
- Issues over the week end
- DAQ, gluon04, No PS-trigger on display (DAQ-trigger ok!)
- Data Monitoring
- FCAL performance
- beam intensity issues this morning 7am .... Moday morning start of the work day
- Today:
- Safety walk through
- Tagger beam line vacuum
Friday, Oct 19 at 08:45
- Notes from the past 24 hours:
- Alignment of JD70-105 47um in 10 hours. THANKS TO HOVANES!
- Amo run taken
- Harp scan taken: same beam conditions as on Wednesday evening
- PARA and PERP at 0/90 with new diamond in the books!
- Beam last 24h
- Report:
- Actions Required:
- TAKE DATA!
- Weekly Beam forecast: CEBAF-WhiteBoard
- HallA machine development (Tue.-Wed) may shift to Mon.-Tue.!
- Run Plan:
- WTFATRC
- NEED RC in 2 weeks!
- ANY other business
Thursday, Oct 18 at 08:45
- Notes from the past 24 hours:
- re-tune the beam focus was very unsuccessful looking at enhancement.
- according to Todd beam is out of spec considerably in halld beam line.
- beam focus most likely over-focusing?
- Actions Required:
- photon beam, coherent peak!
- need good beam AND diamond for the week end!
- Weekly Beam forecast: CEBAF-WhiteBoard
- Beam studies Monday, HallC 4hour access
- RF recovery Tuesday, HallC aerogel installation
- Wednesday 7am(?) to Thursday midnight Hall-A beam tune. No beam or only parasitic other halls.
- take advantage of down for installations?
- TAC postpone to Friday 10/26?????
- Reports:
- photon beam spot still perfectly centered
- Data Monitoring?
- Statistics Spreadsheet
- Run Plan