(Monday, October 18)
(Monday, October 18)
Line 16: Line 16:
 
# [https://halldweb.jlab.org/primexd/run_plan/Run_Plan_Fall_2021.pdf Plan:]
 
# [https://halldweb.jlab.org/primexd/run_plan/Run_Plan_Fall_2021.pdf Plan:]
 
#* 8am pass change - start filling the target
 
#* 8am pass change - start filling the target
#* install the FDC chiller power switch - https://logbooks.jlab.org/entry/3925381
+
#** install the FDC chiller power switch - https://logbooks.jlab.org/entry/3925381
#* FCAL work
+
#** FCAL work
#* after beam comes - harp scans
+
#** after beam comes - harp scans
 
#* plan for day/swing on Wednesday - maintenance
 
#* plan for day/swing on Wednesday - maintenance
 +
#** position survey CCAL - requires RadCon survey prior
 +
#** install additional shielding at the left (downstream) PS arm
 +
#** do measurements with magnetometer
 +
#** ...
  
 
=Friday, October 15=
 
=Friday, October 15=

Revision as of 07:27, 18 October 2021

Monday, October 18

  1. Over the weekend:
  2. Remaining issues:
    • tagger NMR not scanning
    • Bleedthrough
  3. Plan:
    • 8am pass change - start filling the target
    • plan for day/swing on Wednesday - maintenance
      • position survey CCAL - requires RadCon survey prior
      • install additional shielding at the left (downstream) PS arm
      • do measurements with magnetometer
      • ...

Friday, October 15

  1. In last 24 hours:
  2. Remaining issues:
  3. Plan:
    • run till 5pm with full target, then with empty over the weekend - inform target group (Chris) when emptying/filling the target
    • pass change on Monday
    • day/swing on Wednesday - maintenance


Thursday, October 14

  1. In last 24 hours:
  2. Remaining issues:
  3. Plan:
    • 2 more shifts with 200 nA and target filled with He then wait for decision from Primex 4 pm meeting.