Run Planning Meeting Notes, October 14 - October 20, 2021

From GlueXWiki
Revision as of 10:52, 17 October 2021 by Pentchev (Talk | contribs) (Monday, October 18)

Jump to: navigation, search

Monday, October 18

  1. Over the weekend:
  2. Remaining issues:
    • tagger NMR not scanning
    • Bleedthrough
  3. Plan:
    • 8am pass change - start filling the target - inform target group (Chris)
    • install the FDC chiller power switch
    • plan for day/swing on Wednesday - maintenance

Friday, October 15

  1. In last 24 hours:
  2. Remaining issues:
  3. Plan:
    • run till 5pm with full target, then with empty over the weekend - inform target group (Chris) when emptying/filling the target
    • pass change on Monday
    • day/swing on Wednesday - maintenance


Thursday, October 14

  1. In last 24 hours:
  2. Remaining issues:
  3. Plan:
    • 2 more shifts with 200 nA and target filled with He then wait for decision from Primex 4 pm meeting.