Run Planning Meeting Notes, October 14 - October 20, 2021

From GlueXWiki
Revision as of 07:27, 18 October 2021 by Pentchev (Talk | contribs) (Monday, October 18)

Jump to: navigation, search

Monday, October 18

  1. Over the weekend:
  2. Remaining issues:
    • tagger NMR not scanning
    • BCAL noise at 10 o'clock
    • Bleedthrough
  3. Plan:
    • 8am pass change - start filling the target
    • plan for day/swing on Wednesday - maintenance
      • position survey CCAL - requires RadCon survey prior
      • install additional shielding at the left (downstream) PS arm
      • do measurements with magnetometer
      • ...

Friday, October 15

  1. In last 24 hours:
  2. Remaining issues:
  3. Plan:
    • run till 5pm with full target, then with empty over the weekend - inform target group (Chris) when emptying/filling the target
    • pass change on Monday
    • day/swing on Wednesday - maintenance


Thursday, October 14

  1. In last 24 hours:
  2. Remaining issues:
  3. Plan:
    • 2 more shifts with 200 nA and target filled with He then wait for decision from Primex 4 pm meeting.