Difference between revisions of "Run Planning Meeting Notes, October 21 - October 27, 2021"
From GlueXWiki
(Created page with "=Thursday, October 21= # Last 24h: #* No beam from 5:20pm Tuesday until ??? due to LCW/power problem #* Work done during the access: #** position survey CCAL - DOESN'T require...") |
(→Thursday, October 21) |
||
Line 10: | Line 10: | ||
#** [https://logbooks.jlab.org/entry/3928742 rebalanced the server power load on rack 13] | #** [https://logbooks.jlab.org/entry/3928742 rebalanced the server power load on rack 13] | ||
# Remaining issues: | # Remaining issues: | ||
− | #* | + | #* communication with accel. w.r.t. tagger magnet - Paul Vasilauskis (Ops group leader): "I am putting out to my staff to contact the hall if they do need to touch the magnet and am looking into adding wording to the magnet screens" |
#* BCAL noise at 10 o'clock | #* BCAL noise at 10 o'clock | ||
#* Bleedthrough | #* Bleedthrough |
Revision as of 23:33, 20 October 2021
Thursday, October 21
- Last 24h:
- No beam from 5:20pm Tuesday until ??? due to LCW/power problem
- Work done during the access:
- position survey CCAL - DOESN'T require RadCon survey
- correct shielding at the left (downstream) PS arm
- magnetic field measurements around CCAL
- 15 FCAL bases replaced and re-terminated one cable
- faulty FDC chiller replaced
- rebalanced the server power load on rack 13
- Remaining issues:
- communication with accel. w.r.t. tagger magnet - Paul Vasilauskis (Ops group leader): "I am putting out to my staff to contact the hall if they do need to touch the magnet and am looking into adding wording to the magnet screens"
- BCAL noise at 10 o'clock
- Bleedthrough
- Plan:
- When the beam is back continue production at 200nA after the usual checks (radiation levels & harp scans)
- Continue running with the solenoid on & target full until Friday or later
- Pass change possible Friday or Saturday
- Expect some downtime Monday daytime for VIP tour