(Thursday, October 21)
(Thursday, October 21)
Line 10: Line 10:
 
#** [https://logbooks.jlab.org/entry/3928742 rebalanced the server power load on rack 13]
 
#** [https://logbooks.jlab.org/entry/3928742 rebalanced the server power load on rack 13]
 
# Remaining issues:
 
# Remaining issues:
 +
#* [https://logbooks.jlab.org/entry/3929404 Tagger hodoscope time shifts]
 
#* communication with accel. w.r.t. tagger magnet - Paul Vasilauskis (Ops group leader): "I am putting out to my staff to contact the hall if they do need to touch the magnet and am looking into adding wording to the magnet screens"
 
#* communication with accel. w.r.t. tagger magnet - Paul Vasilauskis (Ops group leader): "I am putting out to my staff to contact the hall if they do need to touch the magnet and am looking into adding wording to the magnet screens"
 
#* BCAL noise at 10 o'clock
 
#* BCAL noise at 10 o'clock

Revision as of 07:26, 21 October 2021

Thursday, October 21

  1. Last 24h:
  2. Remaining issues:
    • Tagger hodoscope time shifts
    • communication with accel. w.r.t. tagger magnet - Paul Vasilauskis (Ops group leader): "I am putting out to my staff to contact the hall if they do need to touch the magnet and am looking into adding wording to the magnet screens"
    • BCAL noise at 10 o'clock
    • Bleedthrough
  3. Plan:
    • When the beam is back continue production at 200nA after the usual checks (radiation levels & harp scans)
    • Continue running with the solenoid on & target full until Friday or later
    • Pass change possible Friday or Saturday
    • Expect some downtime Monday daytime for VIP tour