Run Planning Meeting Notes, October 21 - October 27, 2021
From GlueXWiki
Revision as of 20:49, 20 October 2021 by Njarvis (Talk | contribs) (Created page with "=Thursday, October 21= # Last 24h: #* No beam from 5:20pm Tuesday until ??? due to LCW/power problem #* Work done during the access: #** position survey CCAL - DOESN'T require...")
Thursday, October 21
- Last 24h:
- No beam from 5:20pm Tuesday until ??? due to LCW/power problem
- Work done during the access:
- position survey CCAL - DOESN'T require RadCon survey
- correct shielding at the left (downstream) PS arm
- magnetic field measurements around CCAL
- 15 FCAL bases replaced and re-terminated one cable
- faulty FDC chiller replaced
- rebalanced the server power load on rack 13
- Remaining issues:
- ? tagger NMR not scanning (communication with accel. w.r.t. tagger magnet)
- BCAL noise at 10 o'clock
- Bleedthrough
- Plan:
- When the beam is back continue production at 200nA after the usual checks (radiation levels & harp scans)
- Continue running with the solenoid on & target full until Friday or later
- Pass change possible Friday or Saturday
- Expect some downtime Monday daytime for VIP tour