Difference between revisions of "Run Planning Meeting Notes, September 10 - 16, 2020"

From GlueXWiki
Jump to: navigation, search
(Friday, September 11 at 8:45)
m (Wednesday, September 16 at 8:45)
 
(32 intermediate revisions by the same user not shown)
Line 12: Line 12:
 
#  at MEDCON 5 the lab has no cafeteria services because eating "cafeteria style" (eating in common from prepared food) is inconsistent with COVID-19 controls. Staging food in the counting room to share is inconsistent with MEDCON 5 COVID-19 controls.  
 
#  at MEDCON 5 the lab has no cafeteria services because eating "cafeteria style" (eating in common from prepared food) is inconsistent with COVID-19 controls. Staging food in the counting room to share is inconsistent with MEDCON 5 COVID-19 controls.  
 
#  food and drink consumption - because it requires removing face coverings to consume -  should be limited to packaged food and drink brought for personal use that is consumed while maintaining at least 6 ft. from the nearest person and ideally, consumed in a separate room from others.
 
#  food and drink consumption - because it requires removing face coverings to consume -  should be limited to packaged food and drink brought for personal use that is consumed while maintaining at least 6 ft. from the nearest person and ideally, consumed in a separate room from others.
 +
 +
=Wednesday, September 16 at 8:45=
 +
# Last 48 hours:
 +
#*Production
 +
#*On Monday:
 +
#**Gluex Production from 6am-10am. Then 2h of beam study,
 +
#**Production resumed from noon to 2:20pm when the beam went down due to power supply failure in the injector. When beam came back (6pm), it was used for 5:30h of beam study.
 +
#**Production resumed at 23:30.
 +
#*On Tuesday:
 +
#**Production until 7:45am when South Linac went down due to cryo problem (compressor 4 controller problem in SL CHL). Production resumed at 21:50. Meanwhile Beni did ST efficiency runs and cosmic runs.
 +
#Accesses:
 +
#***Monday 10am: Vladimir Berdnikov (PS area)
 +
#***Monday 10am, tagger vault. Josh F.
 +
#***Monday 4:15pm: Lubomir and Kondo (PS area, 1-2h), to install and check a HV module for the GEM setup.
 +
#***Monday Vladimir and Alex Somov, in the PS area (other side).
 +
# Reports/issues:
 +
#*Solenoid Alarm for Coil 4 vacuum (know problem) [https://logbooks.jlab.org/entry/3849070 Mark S.'s report] [https://logbooks.jlab.org/entry/3849078 Tim's report]
 +
#*[https://logbooks.jlab.org/entry/3848701 Red lines on monitoring plots do not match peaks (Elton)]
 +
#*[https://logbooks.jlab.org/entry/3848404 New PWO crystals installed (A. Somov et al.)]
 +
#*[https://logbooks.jlab.org/entry/3847991 Relative Photon Efficiencies Elton, Alex A.]
 +
# Run plan
 +
#* Continue production runs
 +
#* Friday Sept. 18th, 6am: Hall C pass change from 5 to 1 pass. We should request to run on our own slit.
 +
#*Next RC meetings at 8:30am?
 +
#* Special tasks remaining:
 +
#**Periodic harp scans (last one done on [https://logbooks.jlab.org/entry/3841546 Sept. 5th]). The rates and transmission [https://logbooks.jlab.org/entry/3845189 have been stable]
 +
#**Check CCal active basis with 2nA beam. 2h. A. Somov. To be scheduled when Hall C is at 1-pass, Hall A is down and we have our own slit.
 +
#**Pair Spec. test. 1h. A. Somov. After the CCal check.
 +
 +
=Monday, September 14 at 8:45=
 +
# Last 72 hours:
 +
#*Production
 +
#*On Friday:
 +
#**After being down since 2am (vacuum issue), the beam came back at 9am and a empty target run started (target was emptied during the beam down time). Beam down after 30min due to NLvacuum issue and 5th pass separator issue. Beam came back at 15:15. Another  empty target run (1h+) was taken and then production resumed.
 +
#**During beam down time, Kondo accessed the Hall to install a new power supply for a GEM (PS area).
 +
#*Saturday: production
 +
#**Beam off from 4pm to 6:30pm due to Klystron change. Sergey accessed the Hall for GEM/TRD work. 
 +
#*Sunday:
 +
#** Owl, 1am: scheduled Raster test (Richard Jones. Mike McCaughan). Beam went down at 1:12am, (Chopper + 2L13 issues) and the test had to be postponed. Beam came back at about 4pm.
 +
#** swing: A. Somov  worked on SRC trigger fine tuning. Started data taking with SRC trigger at 11pm until rather test at 3:45am next day.
 +
#*Monday:
 +
#** [https://logbooks.jlab.org/entry/3847748 Owl, 3:45-5:15am: re-scheduled Raster test (Richard Jones. Mike McCaughan)]. Test was cut short by the PD at 5:15am because it caused too much trip.
 +
#** Back to SRC trigger data taking for 30min (accidentally, but the data is welcome. Run 73141) and then standard production.
 +
# Reports/issues:
 +
#* RCDB/DAQ test (shorten stop run duration.) Dimitri/Sergey.
 +
#* [https://logbooks.jlab.org/entry/3847802 Raster test (Richard, Mike McCaughan)]
 +
#*[https://logbooks.jlab.org/entry/3846185 Ram disk filling (David Lawrence)]
 +
#*[https://logbooks.jlab.org/entry/3846425 RootSpy fails on new run (Mark Dalton)]
 +
# Run plan
 +
#* Continue production runs
 +
#* Monday Sept. 14th: beam study.
 +
#**10am - 11am/noon: beam study (access to hall allowed).
 +
#**11am - 16:15: physics beam.
 +
#**16:15 - 21:15: beam study (access to hall allowed).
 +
#**Access list:
 +
#***10am: Vladimir Berdnikov (PS area, 1h)
 +
#***10am, tagger vault. Josh F.
 +
#***4:15pm: Lubomir and Kondo (PS area, 1-2h), to install and check a HV module for the GEM setup.
 +
#* Friday Sept. 18th, 6am: Hall C pass change from 5 to 1 pass. We should request to run on our own slit.
 +
#* Special tasks remaining:
 +
#**Periodic harp scans (last one done on [https://logbooks.jlab.org/entry/3841546 Sept. 5th]). The rates and transmission [https://logbooks.jlab.org/entry/3845189 have been stable]
 +
#**Beam rastering test
 +
#**Check CCal active basis with 2nA beam. 2h. A. Somov. To be scheduled when Hall C is at 1-pass, Hall A is down and we have our own slit.
  
 
=Friday, September 11 at 8:45=
 
=Friday, September 11 at 8:45=
 
# Last 24 hours:
 
# Last 24 hours:
 +
#*Production, but RF recovery+NL troubles+vacuum issue resulted in only about 6h of useable beam.
 +
#*Hall accesses by Lubomir (to reset a crate) and Mark D. ([https://logbooks.jlab.org/entry/3845273 to fix non-working BCal pulser]) during scheduled beam down time.
 +
#*Hall access by Vladimir Berdnikov (PS area) to reinsert crystals and check communication. <!-- Vlad cell cell is 757-277-8135-->
 
# Reports/issues:
 
# Reports/issues:
#*Hall accesses by Lubomir and Mark D. ([https://logbooks.jlab.org/entry/3845273 to fix non-working BCal pulser]) during scheduled beam down time.
 
 
#*[https://logbooks.jlab.org/entry/3845380 Spikes in AC x/y]
 
#*[https://logbooks.jlab.org/entry/3845380 Spikes in AC x/y]
 +
#*[https://logbooks.jlab.org/entry/3845485 BCAL Hadronic Efficiencies]
 
# Run plan
 
# Run plan
 +
#* One last empty target run (2h) (current diamond radiator config., 350 nA)
 
#* Continue production runs
 
#* Continue production runs
#* SRC trigger fine tuning. 2h A. Somov   
+
#* SRC trigger fine tuning + taking data with SRC trigger. 1 shift (Saturday swing). A. Somov   
#* Tuesday Sept. 15th: 3h of beam study expected
+
#* Monday Sept. 14th: 10am-16:00: 6h of beam study.
#**Access planed to the PS area to reinsert the WB and check the communication. (Vladimir Berdnikov, 1h). If unforeseen beatdown time, access can be done earlier on opportunistic basis (any time except Friday 6pm to Saturday 7am).  <!-- Vlad cell cell is 757-277-8135-->
+
#*Tuesday Sept. 15th: due to All Hand Meeting at 9am, RC meeting is cancelled (unless something important happens).   
 
#* Thursday or Friday Sept. 17th/18th: Hall C pass change from 5 to 1 pass. We should request to run on our own slit.
 
#* Thursday or Friday Sept. 17th/18th: Hall C pass change from 5 to 1 pass. We should request to run on our own slit.
 
#* Special tasks remaining:
 
#* Special tasks remaining:
 
#**Periodic harp scans (last one done on [https://logbooks.jlab.org/entry/3841546 Sept. 5th]). The rates and transmission [https://logbooks.jlab.org/entry/3845189 have been stable]
 
#**Periodic harp scans (last one done on [https://logbooks.jlab.org/entry/3841546 Sept. 5th]). The rates and transmission [https://logbooks.jlab.org/entry/3845189 have been stable]
#**One last empty target run (2h)
 
 
#**Beam rastering test  
 
#**Beam rastering test  
 
#**Check CCal active basis with 2nA beam. 2h. A. Somov. To be scheduled when Hall C is at 1-pass, Hall A is down and we have our own slit.
 
#**Check CCal active basis with 2nA beam. 2h. A. Somov. To be scheduled when Hall C is at 1-pass, Hall A is down and we have our own slit.
Line 32: Line 98:
 
=Thursday, September 10 at 8:45=
 
=Thursday, September 10 at 8:45=
 
# Last 24 hours:
 
# Last 24 hours:
 +
#* Production, with beam available for most of the day. A lot of beam trips however, which will be taken care of by impromptu RF recovery tomorrow.
 
# Reports/issues:
 
# Reports/issues:
 
#*[https://logbooks.jlab.org/entry/3844529 BCal hot channel] (Fixed by Sergey)
 
#*[https://logbooks.jlab.org/entry/3844529 BCal hot channel] (Fixed by Sergey)

Latest revision as of 09:03, 16 September 2020

<- Back to Run Coordination Meetings:Summer2020

Integrated trigger count

GlueX Statistics Run Sheet


MEDCON 5 restrictions (Bob May email)

  1. adhere to counting room capacity restrictions
  2. maintain 6 ft. separation (briefly passing another person inside 6 ft. while moving about the counting room is inevitable and is OK)
  3. wear masks anytime more than one person present in the counting room
  4. at MEDCON 5 the lab has no cafeteria services because eating "cafeteria style" (eating in common from prepared food) is inconsistent with COVID-19 controls. Staging food in the counting room to share is inconsistent with MEDCON 5 COVID-19 controls.
  5. food and drink consumption - because it requires removing face coverings to consume - should be limited to packaged food and drink brought for personal use that is consumed while maintaining at least 6 ft. from the nearest person and ideally, consumed in a separate room from others.

Wednesday, September 16 at 8:45

  1. Last 48 hours:
    • Production
    • On Monday:
      • Gluex Production from 6am-10am. Then 2h of beam study,
      • Production resumed from noon to 2:20pm when the beam went down due to power supply failure in the injector. When beam came back (6pm), it was used for 5:30h of beam study.
      • Production resumed at 23:30.
    • On Tuesday:
      • Production until 7:45am when South Linac went down due to cryo problem (compressor 4 controller problem in SL CHL). Production resumed at 21:50. Meanwhile Beni did ST efficiency runs and cosmic runs.
  2. Accesses:
        • Monday 10am: Vladimir Berdnikov (PS area)
        • Monday 10am, tagger vault. Josh F.
        • Monday 4:15pm: Lubomir and Kondo (PS area, 1-2h), to install and check a HV module for the GEM setup.
        • Monday Vladimir and Alex Somov, in the PS area (other side).
  3. Reports/issues:
  4. Run plan
    • Continue production runs
    • Friday Sept. 18th, 6am: Hall C pass change from 5 to 1 pass. We should request to run on our own slit.
    • Next RC meetings at 8:30am?
    • Special tasks remaining:
      • Periodic harp scans (last one done on Sept. 5th). The rates and transmission have been stable
      • Check CCal active basis with 2nA beam. 2h. A. Somov. To be scheduled when Hall C is at 1-pass, Hall A is down and we have our own slit.
      • Pair Spec. test. 1h. A. Somov. After the CCal check.

Monday, September 14 at 8:45

  1. Last 72 hours:
    • Production
    • On Friday:
      • After being down since 2am (vacuum issue), the beam came back at 9am and a empty target run started (target was emptied during the beam down time). Beam down after 30min due to NLvacuum issue and 5th pass separator issue. Beam came back at 15:15. Another empty target run (1h+) was taken and then production resumed.
      • During beam down time, Kondo accessed the Hall to install a new power supply for a GEM (PS area).
    • Saturday: production
      • Beam off from 4pm to 6:30pm due to Klystron change. Sergey accessed the Hall for GEM/TRD work.
    • Sunday:
      • Owl, 1am: scheduled Raster test (Richard Jones. Mike McCaughan). Beam went down at 1:12am, (Chopper + 2L13 issues) and the test had to be postponed. Beam came back at about 4pm.
      • swing: A. Somov worked on SRC trigger fine tuning. Started data taking with SRC trigger at 11pm until rather test at 3:45am next day.
    • Monday:
  2. Reports/issues:
  3. Run plan
    • Continue production runs
    • Monday Sept. 14th: beam study.
      • 10am - 11am/noon: beam study (access to hall allowed).
      • 11am - 16:15: physics beam.
      • 16:15 - 21:15: beam study (access to hall allowed).
      • Access list:
        • 10am: Vladimir Berdnikov (PS area, 1h)
        • 10am, tagger vault. Josh F.
        • 4:15pm: Lubomir and Kondo (PS area, 1-2h), to install and check a HV module for the GEM setup.
    • Friday Sept. 18th, 6am: Hall C pass change from 5 to 1 pass. We should request to run on our own slit.
    • Special tasks remaining:
      • Periodic harp scans (last one done on Sept. 5th). The rates and transmission have been stable
      • Beam rastering test
      • Check CCal active basis with 2nA beam. 2h. A. Somov. To be scheduled when Hall C is at 1-pass, Hall A is down and we have our own slit.

Friday, September 11 at 8:45

  1. Last 24 hours:
    • Production, but RF recovery+NL troubles+vacuum issue resulted in only about 6h of useable beam.
    • Hall accesses by Lubomir (to reset a crate) and Mark D. (to fix non-working BCal pulser) during scheduled beam down time.
    • Hall access by Vladimir Berdnikov (PS area) to reinsert crystals and check communication.
  2. Reports/issues:
  3. Run plan
    • One last empty target run (2h) (current diamond radiator config., 350 nA)
    • Continue production runs
    • SRC trigger fine tuning + taking data with SRC trigger. 1 shift (Saturday swing). A. Somov
    • Monday Sept. 14th: 10am-16:00: 6h of beam study.
    • Tuesday Sept. 15th: due to All Hand Meeting at 9am, RC meeting is cancelled (unless something important happens).
    • Thursday or Friday Sept. 17th/18th: Hall C pass change from 5 to 1 pass. We should request to run on our own slit.
    • Special tasks remaining:
      • Periodic harp scans (last one done on Sept. 5th). The rates and transmission have been stable
      • Beam rastering test
      • Check CCal active basis with 2nA beam. 2h. A. Somov. To be scheduled when Hall C is at 1-pass, Hall A is down and we have our own slit.

Thursday, September 10 at 8:45

  1. Last 24 hours:
    • Production, with beam available for most of the day. A lot of beam trips however, which will be taken care of by impromptu RF recovery tomorrow.
  2. Reports/issues:
  3. Run plan
    • Continue production runs
    • Large amount of beam trips due to Hall A beam steering problem. Beam will be down at (tentatively) 9am today for an expected 1 or 2h to address the problem.
    • Tuesday Sept. 15th: 3h of beam study expected
    • Thursday or Friday Sept. 17th/18th: Hall C pass change from 5 to 1 pass
    • Special tasks remaining:
      • Beam rastering test
      • Periodic harp scans (last one done on Sept. 5th). The rates and transmission have been stable
      • Empty target run?