Run Planning Meeting Notes, September 16 - September 23, 2021

From GlueXWiki
Revision as of 08:45, 17 September 2021 by Billlee (Talk | contribs) (Tuesday, September 17)

Jump to: navigation, search

<- Back to Run Coordination Meetings:Summer2021

Tuesday, September 16

  1. Last 24 hours:
  2. Report/issue
  3. Run plan
    • Wait for beam delivery. Begin experiment commissioning. Run plan

Tuesday, September 17

  1. Last 24 hours:
  2. HARP Scan results: https://logbooks.jlab.org/entry/3906296
  3. Report/issue
    • AC cable wired backward? : https://logbooks.jlab.org/entry/3906359
      • Radcon is escorting Nick into the collimator cave for checking
    • Counting house microphone issue:
      • Improved significantly by the new microphone by Matt
      • A longer USB to micro USB cable will further improve the remote shift experience
    • PS Magnet is still turned off
  4. Run plan
    • Run plan
    • Complete beam configuration (Hovanes) after fixing Active collimator
    • Detector checkout
      • Contact persons: Rachard (): richard.t.jones@uconn.edu, Drew: andrew.p.smith@duke.edu , Sasha: andrew.p.smith@duke.edu, Igal: ijaegle@jlab.org , Tyler: .
    • Low Current 2nA run this afternoon (during Mike's shift)
    • Empty target run again overnight?