<- Back to [[Run Coordination Meetings:Summer2021]]
 
<- Back to [[Run Coordination Meetings:Summer2021]]
 +
 +
=Wednesday, September 29=
 +
#In last 24 hours:
 +
#* Early Riser: https://logbooks.jlab.org/entry/3914295
 +
#* Owl summary: https://logbooks.jlab.org/entry/3914209
 +
#* Swing summary: https://logbooks.jlab.org/entry/3913887
 +
#* CDC baseline calibration https://logbooks.jlab.org/entry/3913755 (Bene)
 +
#* FCAL HV scan https://logbooks.jlab.org/entry/3913887 (Simon) https://logbooks.jlab.org/entry/3913909 (ig)
 +
#* Beam was back around 7:30 pm
 +
#** Radiation level https://logbooks.jlab.org/entry/3914082 https://logbooks.jlab.org/entry/3914082 https://logbooks.jlab.org/entry/3913887 (Alexandre)
 +
#** HARP scan https://logbooks.jlab.org/entry/3914082
 +
#** Be 200 nA https://logbooks.jlab.org/entry/3914169 (Sasha): ~1B trigger (1.6/10)
 +
#* Beam away at 6:30 am until 6 pm (maintenance day)
 +
#Issues:
 +
#* FCAL:
 +
#** Dead channels https://logbooks.jlab.org/entry/3914386 (ig)
 +
#** 53 suspicious channels https://logbooks.jlab.org/entry/3913947 https://logbooks.jlab.org/entry/3913739 (Rebecca/Mark/Malte)
 +
#* Sweep magnet turn off https://logbooks.jlab.org/entry/3913900 (Simon)
 +
#* Bleedthrough
 +
#[https://halldweb.jlab.org/primexd/run_plan/Run_Plan_Fall_2021.pdf Plan:]
 +
#* [https://logbooks.jlab.org/entry/3913494 Before taking data: check radiation level and beam quality] (HARP scan)
 +
#* 50 nA with CDC & FDC turn on (2 shifts), Lubomir must be around
 +
#* 100 nA CDC & FDC turn off (2 shifts)
 +
#* 200 nA CDC & FDC turn off (8.4 shifts)
 +
#* Remove Be target to take empty target
 +
 +
=Tuesday, September 28=
 +
#In last 24 hours:
 +
#* No beam
 +
#Issues:
 +
#* Follow-up on possible SC issue https://logbooks.jlab.org/entry/3913352
 +
#* 53 FCAL blocks are suspicious https://logbooks.jlab.org/entry/3913620
 +
#* Bleedthrough
 +
#[https://halldweb.jlab.org/primexd/run_plan/Run_Plan_Fall_2021.pdf Plan:]
 +
#* RadCon will sweep HallD around 1 pm
 +
#* Be with 50nA and both chambers turn on (two shifts)
 +
 
=Monday, September 27=
 
=Monday, September 27=
 
# In last 72 hours:
 
# In last 72 hours:
Line 8: Line 45:
 
#* Swing summary: https://logbooks.jlab.org/entry/3912060
 
#* Swing summary: https://logbooks.jlab.org/entry/3912060
 
#* Sunday 8am to Monday 8am summary: no beam
 
#* Sunday 8am to Monday 8am summary: no beam
 +
#** FDC1 Cell1 efficiency went up https://logbooks.jlab.org/entry/3913057 (Lubomir)
 +
#** New TAGH HV https://logbooks.jlab.org/entry/3913029 (Sasha)
 +
#** FCAL pi0 calibration divided into 3 period: Summer 2020 HV, Summer 2020 HV - 6V, and Fall 2021 HV (214 HV adjusted) https://logbooks.jlab.org/entry/3913166 (ig)
 
#* Saturday 8am to Sunday 8am summary:
 
#* Saturday 8am to Sunday 8am summary:
 
#** No beam from 10am to 7pm
 
#** No beam from 10am to 7pm
Line 23: Line 63:
 
#** HARP scan https://logbooks.jlab.org/entry/3912325 https://logbooks.jlab.org/entry/3912325 https://logbooks.jlab.org/entry/3912325
 
#** HARP scan https://logbooks.jlab.org/entry/3912325 https://logbooks.jlab.org/entry/3912325 https://logbooks.jlab.org/entry/3912325
 
# Issues
 
# Issues
#* TAGM wrongly cabling https://logbooks.jlab.org/entry/3912516 and may have still an issue https://logbooks.jlab.org/entry/3912822 (Beni/Richard)
+
#* TAGM wrongly cabling https://logbooks.jlab.org/entry/3912516 / https://logbooks.jlab.org/entry/3912822 (Beni/Richard)
 
#* No Beam https://logbooks.jlab.org/entry/3912495 https://logbooks.jlab.org/entry/3912567 (Jay, PD)
 
#* No Beam https://logbooks.jlab.org/entry/3912495 https://logbooks.jlab.org/entry/3912567 (Jay, PD)
 
#* TAGH discriminator scalers in EPICS froze https://logbooks.jlab.org/entry/3912490 (Hovanes)
 
#* TAGH discriminator scalers in EPICS froze https://logbooks.jlab.org/entry/3912490 (Hovanes)
 +
#* Possible issue with SC https://logbooks.jlab.org/entry/3912992 (Sean)
 
#* Bleedthrough
 
#* Bleedthrough
 
# [https://halldweb.jlab.org/primexd/run_plan/Run_Plan_Fall_2021.pdf Plan]
 
# [https://halldweb.jlab.org/primexd/run_plan/Run_Plan_Fall_2021.pdf Plan]
 
#* Maintenance
 
#* Maintenance
#** FCAL (Rebecca/Malte/Mark)
+
#** FCAL https://logbooks.jlab.org/entry/3912930 (Rebecca/Malte/Mark)
 
#** Swap one MPGD prototype under test with a new one (Kondo/Lubomir)
 
#** Swap one MPGD prototype under test with a new one (Kondo/Lubomir)
  

Latest revision as of 20:54, 29 September 2021

<- Back to Run Coordination Meetings:Summer2021

Wednesday, September 29

  1. In last 24 hours:
  2. Issues:
  3. Plan:

Tuesday, September 28

  1. In last 24 hours:
    • No beam
  2. Issues:
  3. Plan:
    • RadCon will sweep HallD around 1 pm
    • Be with 50nA and both chambers turn on (two shifts)

Monday, September 27

  1. In last 72 hours:
  2. Issues
  3. Plan

Friday, September 24

  1. In last 24 hours:
  2. Issues
  3. Plan
    • Compton with Be target at low intensity

Thursday, September 23

  1. In last 24 hours:
  2. Issues
  3. Plan for the day
    • tagm studies by Richard
    • FDC straight track studies by Lubomir