Difference between revisions of "Run Planning Meeting Notes, September 29 - October 5, 2022"
From GlueXWiki
m (→Issues) |
m |
||
Line 8: | Line 8: | ||
Back to [[Run Coordination Meetings:Fall2022]] | Back to [[Run Coordination Meetings:Fall2022]] | ||
+ | |||
+ | =Friday, September 30= | ||
+ | === Past 24 hours === | ||
+ | *Long maintenance day dedicated to RF recovery and injector setup in preparation for Hall A coming online | ||
+ | ** | ||
+ | ** | ||
+ | *Alex A. added back the standard physics monitoring histograms to the rootspy GUI | ||
+ | *Shift summaries | ||
+ | **[ 0400-1000 29/09] | ||
+ | **[ 2200-0400 28-29/09] | ||
+ | **[https://logbooks.jlab.org/entry/4048646 1600-2200 28/09] | ||
+ | **[https://logbooks.jlab.org/entry/4048507 1000-1600 28/09] | ||
+ | **[https://logbooks.jlab.org/entry/4048368 0400-1000 28/09] | ||
+ | |||
+ | === Issues === | ||
+ | |||
+ | === Plan === | ||
+ | *Continue taking production data on LHe at 200nA. | ||
+ | |||
=Thursday, September 29= | =Thursday, September 29= |
Revision as of 17:17, 29 September 2022
Meetings are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)
Hall D counting room white board
Back to Run Coordination Meetings:Fall2022
Contents
Friday, September 30
Past 24 hours
- Long maintenance day dedicated to RF recovery and injector setup in preparation for Hall A coming online
- Alex A. added back the standard physics monitoring histograms to the rootspy GUI
- Shift summaries
- [ 0400-1000 29/09]
- [ 2200-0400 28-29/09]
- 1600-2200 28/09
- 1000-1600 28/09
- 0400-1000 28/09
Issues
Plan
- Continue taking production data on LHe at 200nA.
Thursday, September 29
Past 24 hours
- Helium target was filled around 1:15PM yesterday.
- 2.5B triggers collected on helium target so far.
- Last run group: Empty Target PS triggers accounted for 33% of Empty+Full data set.
- Currently taking cosmics.
- Shift summaries
Issues
- 1.5hr downtime overnight from CPS breaker trip.
- FCAL Base lockup reset
Plan
- Maintenance Day
- Hall in controlled access.
- Walkthrough training at 10AM.
- When beam is back, we will continue taking production data on LHe at 200nA.