Difference between revisions of "Run Planning Meeting Notes, September 29 - October 5, 2022"

From GlueXWiki
Jump to: navigation, search
m
m (Past 24 hours)
Line 14: Line 14:
 
**
 
**
 
**
 
**
*Alex A. added back the standard physics monitoring histograms to the rootspy GUI
+
*Alex A. added back the standard physics monitoring histograms to the rootspy GUI [https://halldweb.jlab.org/data_monitoring/Plot_Browser.html?minRunNum=110930&maxRunNum=110937&RunPeriod=RunPeriod-2022-08&Version=rawdata_ver00&Plot=HistMacro_PID&rcdb_query=daq_run%3D%3D%27PHYSICS_PRIMEX%27%20and%20event_count%20%3E%20500000%20and%20collimator_diameter%20%21%3D%20%27Blocking%27]
 
*Shift summaries
 
*Shift summaries
 
**[ 0400-1000 29/09]
 
**[ 0400-1000 29/09]

Revision as of 08:19, 30 September 2022

Meetings are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)

MCC whiteboard

Hall D counting room white board

Hall D Logbook

Back to Run Coordination Meetings:Fall2022

Friday, September 30

Past 24 hours

  • Long maintenance day dedicated to RF recovery and injector setup in preparation for Hall A coming online
  • Alex A. added back the standard physics monitoring histograms to the rootspy GUI [1]
  • Shift summaries

Issues

Plan

  • Continue taking production data on LHe at 200nA.


Thursday, September 29

Past 24 hours

Issues

Plan

  • Maintenance Day
    • Hall in controlled access.
    • Walkthrough training at 10AM.
  • When beam is back, we will continue taking production data on LHe at 200nA.