Run Planning Meeting Notes, September 29 - October 5, 2022

From GlueXWiki
Revision as of 08:30, 30 September 2022 by Andrsmit (Talk | contribs) (Past 24 hours)

Jump to: navigation, search

Meetings are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)

MCC whiteboard

Hall D counting room white board

Hall D Logbook

Back to Run Coordination Meetings:Fall2022

Friday, September 30

Past 24 hours

  • Long maintenance day dedicated to RF recovery and injector setup in preparation for Hall A coming online
    • We collected 43.6M raw-mode cosmics events since yesterday morning.
  • Beam was restored to Hall D at 11PM last night. We completed the accelerator harp scans on 5C11/B and our radiator wire scan.
  • While we were setting up for production after the harp scans, there was an issue with RF dropping out of HV. Beam has been down since then.
  • Alex A. added back the standard physics monitoring histograms to the rootspy GUI [1]
  • Shift summaries

Issues

Plan

  • Once beam is back, re-do harp scans.
  • Continue taking production data on LHe at 200nA today and over the weekend.

Thursday, September 29

Past 24 hours

Issues

Plan

  • Maintenance Day
    • Hall in controlled access.
    • Walkthrough training at 10AM.
  • When beam is back, we will continue taking production data on LHe at 200nA.