(Thursday, September 30)
Line 7: Line 7:
 
#* Swing summary:
 
#* Swing summary:
 
#* Day summary: https://logbooks.jlab.org/entry/3914472
 
#* Day summary: https://logbooks.jlab.org/entry/3914472
 
 
#* Before beam comes back:
 
#* Before beam comes back:
 
#** [https://logbooks.jlab.org/entry/3914628 BCAL pedestal calibration] (Sergey)
 
#** [https://logbooks.jlab.org/entry/3914628 BCAL pedestal calibration] (Sergey)

Revision as of 15:39, 29 September 2021

<- Back to Run Coordination Meetings:Summer2021

Thursday, September 30

  1. In last 24 hours:
  1. Issues:
  1. Plan:
    • Before taking data: check radiation level and beam quality (HARP scan)
    • 50 nA with CDC & FDC turn on (2 shifts), Lubomir must be around
    • 100 nA CDC & FDC turn off (2 shifts)
    • 200 nA CDC & FDC turn off (8.4 shifts)
    • Remove Be target to take empty target