Difference between revisions of "Run Planning Meeting Notes, September 30 - October 6, 2021"

From GlueXWiki
Jump to: navigation, search
Line 7: Line 7:
 
#* Swing summary:
 
#* Swing summary:
 
#* Day summary: https://logbooks.jlab.org/entry/3914472
 
#* Day summary: https://logbooks.jlab.org/entry/3914472
 
 
#* Before beam comes back:
 
#* Before beam comes back:
 
#** [https://logbooks.jlab.org/entry/3914628 BCAL pedestal calibration] (Sergey)
 
#** [https://logbooks.jlab.org/entry/3914628 BCAL pedestal calibration] (Sergey)
 
+
#
 
#Issues:
 
#Issues:
 
#* FCAL:  
 
#* FCAL:  
Line 17: Line 16:
 
#* Sweep magnet turn off https://logbooks.jlab.org/entry/3913900 (Simon)
 
#* Sweep magnet turn off https://logbooks.jlab.org/entry/3913900 (Simon)
 
#* Bleedthrough
 
#* Bleedthrough
 
 
#[https://halldweb.jlab.org/primexd/run_plan/Run_Plan_Fall_2021.pdf Plan:]
 
#[https://halldweb.jlab.org/primexd/run_plan/Run_Plan_Fall_2021.pdf Plan:]
 
#* Before taking data: check radiation level and beam quality (HARP scan)
 
#* Before taking data: check radiation level and beam quality (HARP scan)

Revision as of 15:39, 29 September 2021

<- Back to Run Coordination Meetings:Summer2021

Thursday, September 30

  1. In last 24 hours:
  2. Issues:
  3. Plan:
    • Before taking data: check radiation level and beam quality (HARP scan)
    • 50 nA with CDC & FDC turn on (2 shifts), Lubomir must be around
    • 100 nA CDC & FDC turn off (2 shifts)
    • 200 nA CDC & FDC turn off (8.4 shifts)
    • Remove Be target to take empty target