Difference between revisions of "Run Planning Meeting Notes, September 30 - October 6, 2021"

From GlueXWiki
Jump to: navigation, search
(Thursday, September 30)
Line 11: Line 11:
 
#** [https://logbooks.jlab.org/entry/3914628 BCAL pedestal calibration] (Sergey)
 
#** [https://logbooks.jlab.org/entry/3914628 BCAL pedestal calibration] (Sergey)
 
#** [https://logbooks.jlab.org/entry/3914670 FCAL base replacement][https://logbooks.jlab.org/entry/3914697 Communication issue resolved](Rebecca/Mark/Malte)
 
#** [https://logbooks.jlab.org/entry/3914670 FCAL base replacement][https://logbooks.jlab.org/entry/3914697 Communication issue resolved](Rebecca/Mark/Malte)
 +
#** FCAL HV scan (Igal)
 
#* [https://logbooks.jlab.org/entry/3914822 Timing calibration update] (Sean)
 
#* [https://logbooks.jlab.org/entry/3914822 Timing calibration update] (Sean)
 
#Issues:
 
#Issues:

Revision as of 08:32, 30 September 2021

<- Back to Run Coordination Meetings:Summer2021

Thursday, September 30

  1. In last 24 hours:
  2. Issues:
  3. Plan:
    • Before taking data: check radiation level and beam quality (HARP scan)
    • 50 nA with CDC & FDC turn on (2 shifts), Lubomir must be around
    • 100 nA CDC & FDC turn off (2 shifts)
    • 200 nA CDC & FDC turn off (8.4 shifts)
    • Remove Be target to take empty target