(Friday, October 1)
(Friday, October 1)
Line 3: Line 3:
 
=Friday, October 1=
 
=Friday, October 1=
 
#In last 24 hours:
 
#In last 24 hours:
#* Beam came back around 17:40. After 2h long downtime and DAQ trouble, [https://logbooks.jlab.org/entry/3915704 production runs started at 2:42am].
+
#* Beam came back around 17:40. After 2h long downtime and DAQ trouble, [https://logbooks.jlab.org/entry/3915704 production runs started at 2:42 am].
 
#** [https://logbooks.jlab.org/entry/3915397 Radiation Level]: OK
 
#** [https://logbooks.jlab.org/entry/3915397 Radiation Level]: OK
 
#** [https://logbooks.jlab.org/entry/3915472 Harp scan]: OK
 
#** [https://logbooks.jlab.org/entry/3915472 Harp scan]: OK

Revision as of 08:18, 1 October 2021

<- Back to Run Coordination Meetings:Summer2021

Friday, October 1

  1. In last 24 hours:
  2. Issues:
    • Bleedthrough
  3. Plan:
    • Before taking data: check radiation level and beam quality (HARP scan)
    • 50 nA with CDC & FDC turn on (2 shifts), Lubomir must be around
    • 100 nA CDC & FDC turn off (2 shifts)
    • 200 nA CDC & FDC turn off (8.4 shifts)
    • Remove Be target to take empty target (will take 8h. on Monday?)

Thursday, September 30

  1. In last 24 hours:
  2. Issues:
  3. Plan:
    • Before taking data: check radiation level and beam quality (HARP scan)
    • 50 nA with CDC & FDC turn on (2 shifts), Lubomir must be around
    • 100 nA CDC & FDC turn off (2 shifts)
    • 200 nA CDC & FDC turn off (8.4 shifts)
    • Remove Be target to take empty target (will take 8h. on Monday?)