Line 8: Line 8:
 
#Issues:
 
#Issues:
 
#* Bleedthrough
 
#* Bleedthrough
 +
#[https://halldweb.jlab.org/primexd/run_plan/Run_Plan_Fall_2021.pdf Plan:]
 +
#* 50 nA with CDC & FDC turn on (2 shifts), Lubomir must be around
 +
#* 100 nA CDC & FDC turn off (2 shifts)
 +
#* 200 nA CDC & FDC turn off (8.4 shifts)
 +
#* Remove Be target to take empty target (will take 8h. on Monday?)
  
  

Revision as of 17:49, 1 October 2021

<- Back to Run Coordination Meetings:Summer2021

Saturday, October 1, 10:00 am

  1. In last 24 hours:
  2. Issues:
    • Bleedthrough
  3. Plan:
    • 50 nA with CDC & FDC turn on (2 shifts), Lubomir must be around
    • 100 nA CDC & FDC turn off (2 shifts)
    • 200 nA CDC & FDC turn off (8.4 shifts)
    • Remove Be target to take empty target (will take 8h. on Monday?)


Friday, October 1

  1. In last 24 hours:
  2. Issues:
  3. Plan:
    • 50 nA with CDC & FDC turn on (2 shifts), Lubomir must be around
    • 100 nA CDC & FDC turn off (2 shifts)
    • 200 nA CDC & FDC turn off (8.4 shifts)
    • Remove Be target to take empty target (will take 8h. on Monday?)

Thursday, September 30

  1. In last 24 hours:
  2. Issues:
  3. Plan:
    • Before taking data: check radiation level and beam quality (HARP scan)
    • 50 nA with CDC & FDC turn on (2 shifts), Lubomir must be around
    • 100 nA CDC & FDC turn off (2 shifts)
    • 200 nA CDC & FDC turn off (8.4 shifts)
    • Remove Be target to take empty target (will take 8h. on Monday?)