(Wednesday, October 6)
(Wednesday, October 6)
Line 2: Line 2:
 
=Wednesday, October 6=
 
=Wednesday, October 6=
 
#In last 24 hours:
 
#In last 24 hours:
#* Target work (empty --> LHe4 cell) was completed at 17:00, beam came back at 19:45. We took a bleedthru study run, and production runs with 200 nA beam.
+
#* Target work (empty --> LHe4 cell) was completed at 17:00, beam came back at 19:45.
 
#** [https://logbooks.jlab.org/entry/3918490 Radiation Level]: OK
 
#** [https://logbooks.jlab.org/entry/3918490 Radiation Level]: OK
 
#** [https://logbooks.jlab.org/entry/3918685 Harp scan]: looks OK
 
#** [https://logbooks.jlab.org/entry/3918685 Harp scan]: looks OK
 +
#* We took a bleedthru study run, and production runs with 200 nA beam through the night.
 
#* Early Riser summary
 
#* Early Riser summary
 
#* Owl summary
 
#* Owl summary

Revision as of 21:43, 5 October 2021

<- Back to Run Coordination Meetings:Summer2021

Wednesday, October 6

  1. In last 24 hours:
    • Target work (empty --> LHe4 cell) was completed at 17:00, beam came back at 19:45.
    • We took a bleedthru study run, and production runs with 200 nA beam through the night.
    • Early Riser summary
    • Owl summary
    • Swing summary
    • Day summary
  2. Issues:
  3. Plan:

Tuesday, October 5

  1. In last 24 hours:
  2. Issues and reports:
  3. Plan:
    • After target work:
      • Radiation level check and Harp scan
      • Should we take laser OFF data (30min) before hall A comes on line? --> Yes. Set random pulser frequency to 10 kHz.
    • Take data with empty target (He-4 gas target).
      • 4 shifts with a 200 nA beam. Do we need to take data with 100nA/50nA beams?
      • After this empty target run, we will fill the target (0.5 shift) and start production runs.
    • Hall A will come on line tomorrow afternoon/evening. --> After hall A comes back, radiation level check/Harp scan will be performed.
    • For shift workers: FCAL scaler should be checked frequently.

Monday, October 4

  1. In last 24 hours:
  2. Issues:
  3. Plan:

Sunday, October 3, 10:00 am

  1. In last 24 hours:
  2. Issues:
  3. Plan:

Saturday, October 2, 10:00 am

  1. In last 24 hours:
  2. Issues:
  3. Plan:
    • After this 10:00 meeting, we will stop 50 nA production and turn off chambers (Lubomir is on shift), then Sasha will perform rate scan (it will take 40 min). After that, we will move on to 100 nA production.
    • 100 nA CDC & FDC turn off (2 shifts)
    • 200 nA CDC & FDC turn off (8.4 shifts)
    • Remove Be target to take empty target (will take 8h)
      • On Tuesday, there will very likely be a down time (beam studies or another attempt to fix the Hall C tune mode generator).
      • Hall A will come on line on Wed. (tentative schedule)
    • For shift workers: FCAL scaler should be checked frequently.

Friday, October 1

  1. In last 24 hours:
  2. Issues:
  3. Plan:

Thursday, September 30

  1. In last 24 hours:
  2. Issues:
  3. Plan:
    • Before taking data: check radiation level and beam quality (HARP scan)
    • 50 nA with CDC & FDC turn on (2 shifts), Lubomir must be around
    • 100 nA CDC & FDC turn off (2 shifts)
    • 200 nA CDC & FDC turn off (8.4 shifts)
    • Remove Be target to take empty target (will take 8h. on Monday?)