(Created page with "<- Back to Run Coordination Meetings:Summer2020 [https://halldweb.jlab.org/data_monitoring/run_statistics/RunPeriod-2019-11/index.html Integrated trigger count] [https:/...")
 
Line 13: Line 13:
 
#  food and drink consumption - because it requires removing face coverings to consume -  should be limited to packaged food and drink brought for personal use that is consumed while maintaining at least 6 ft. from the nearest person and ideally, consumed in a separate room from others.
 
#  food and drink consumption - because it requires removing face coverings to consume -  should be limited to packaged food and drink brought for personal use that is consumed while maintaining at least 6 ft. from the nearest person and ideally, consumed in a separate room from others.
  
=Wednesday, September 2=
+
=Thursday, September 3=
 
# Last 24 hours:
 
# Last 24 hours:
 
#* 6 am to 9 pm CPP de-installation, [https://logbooks.jlab.org/entry/3839263 GEM/TRD installation]  
 
#* 6 am to 9 pm CPP de-installation, [https://logbooks.jlab.org/entry/3839263 GEM/TRD installation]  
Line 37: Line 37:
 
#** 4 hours: standard FCAL-BCAL trigger at 250 nA (low energy TAGH turned off)
 
#** 4 hours: standard FCAL-BCAL trigger at 250 nA (low energy TAGH turned off)
 
#** 4 hours: standard FCAL-BCAL trigger at 350 nA (low energy TAGH turned off)
 
#** 4 hours: standard FCAL-BCAL trigger at 350 nA (low energy TAGH turned off)
 
=Tuesday, September 1=
 
# Last 24 hours:
 
#* CPP de-installation, GEM/TRD installation started at ~ 6 am
 
#* 0.07956B triggers 0/90 PARA
 
#* [https://logbooks.jlab.org/entry/3838676 CPP test from ~ 8:45 pm up to ~ 6 am] [https://logbooks.jlab.org/entry/3838552][https://logbooks.jlab.org/entry/3838552][https://logbooks.jlab.org/entry/3838857]
 
#* CPP installation finished at ~ 5 pm, beam came back at ~ 8:45 pm
 
# Report/issues
 
#* [https://logbooks.jlab.org/entry/3838549 Energy decrease]
 
#* [https://logbooks.jlab.org/entry/3838677 6 GeV coherent edge]
 
#* [https://logbooks.jlab.org/entry/3838628 Transmission was good][https://logbooks.jlab.org/entry/3838451]
 
#* [https://logbooks.jlab.org/entry/3838760 CDC LV off]
 
# Pending issues:
 
#* TAGM missing channels due to preamp (Nick, Richard). [https://logbooks.jlab.org/entry/3834294 Update]
 
# Run plan
 
#* 6 am to 6 pm CPP de-installation, GEM/TRD installation
 
#* Ramp down the magnet
 
#* [[Summer_2020_DIRC_Commissioning#Preliminary_Schedule| Preliminary schedule for DIRC/GEM/TRD running]]: continues through noon Thursday
 
#** 6 pm to 4 am, 10 hrs no-field run, 50nA on 10^-4 radiator.
 
#** 4 am to 10 am, ramp up magnet
 
#* Diamond alignment?
 
#* TAC run?
 
#* Rastering study?
 
 
=Monday, August 31=
 
# Last 72 hours:
 
#* On Friday, we had no beam during the day until 8 pm
 
#* 12B triggers: 5.56B PERP, 6.07B PARA, and 5.73 N/A (AMO)
 
#* [https://logbooks.jlab.org/entry/3836779 CPP test tasks 1 to 4]
 
#* [https://logbooks.jlab.org/entry/3837217 Hall C requests 1/2 waveplate #1 IN]
 
#* Trigger/DAQ tests for the SRC/CT
 
# Report/issues
 
#* [https://logbooks.jlab.org/entry/3837141 Beam trip too often]
 
#* [https://logbooks.jlab.org/entry/3836407 DIRC, change in configuration]
 
#* Crystal testing
 
#* [https://logbooks.jlab.org/entry/3836576 HARP scan]
 
#* [https://logbooks.jlab.org/entry/3837341 FDC tripped without alarm again]
 
#* Beam energy increases by 6 MeV
 
#* [https://logbooks.jlab.org/entry/3837686 Tagger magnetic field was lowered by ~1% during run # 72934]
 
#* [https://logbooks.jlab.org/entry/3837141 Rootspy, hydra not updating]
 
#* [https://logbooks.jlab.org/entry/3837068 Evidence of Hall A bleed through]
 
#* [https://logbooks.jlab.org/entry/3837021 hydra Status BCAL hot channel, has been like this for a while]
 
#* [https://logbooks.jlab.org/entry/3836843 Unable to move coherent peak to low value]
 
# Pending issues:
 
#* TAGM missing channels due to preamp (Nick, Richard). [https://logbooks.jlab.org/entry/3834294 Update]
 
# Run plan
 
#* [https://halldweb.jlab.org/wiki/index.php/CPP_Test_2020_-_Schedule CPP tests preparation 6 am to 4 pm]
 
#* [https://halldweb.jlab.org/wiki/index.php/CPP_Test_2020_-_Schedule CPP tests until the next morning, 4 pm Ausgust 31 to 6 am Sep 1]
 
#* [https://halldweb.jlab.org/wiki/images/b/b1/CPP_GEM_Test_install_schedule_Aug2020.pdf GEM/TRD tests preparation 6 am to 4 pm Sep 1]
 
 
=Friday, August 28=
 
# Last 24 hours:
 
#* 4.27B trigger
 
#* Beam down for 5hr30mn (weather + communication wrath)
 
#* [https://logbooks.jlab.org/entry/3835844 Nick] and [https://logbooks.jlab.org/entry/3835884 Lubomir] accessed the hall
 
# Report/issues
 
#* [https://logbooks.jlab.org/entry/3835844 DIRC, South Box Group 9 LV current draw]
 
#* [https://logbooks.jlab.org/entry/3835903 CDC] and [https://logbooks.jlab.org/entry/3835896 FDC] HV tripped
 
#* BCAL [https://logbooks.jlab.org/entry/3835879 pulser rebooted] [https://logbooks.jlab.org/entry/3835894 pulser test]
 
#* CPP test, task 1 to 4 not carry out because of [https://cebaf.jlab.org/dtm/open-events?event_id=7494 beam down]
 
# Pending issues:
 
#* TAGM missing channels due to preamp (Nick, Richard). [https://logbooks.jlab.org/entry/3834294 Update]
 
# Run plan
 
#* Beam expected to come back around noon
 
#* Hall access to debug DIRC (and change crystals?)
 
#* Production
 
#* [https://halldweb.jlab.org/wiki/index.php/CPP_Test_2020_-_Schedule CPP test - task 1 to 4 during Ilya's shift]
 
 
===Discussion on trigger/DAQ tests for the SRC/CT===
 
#Sasha requested 5-6 hours on Sunday to do these tests
 
 
===Discussion on CPP and GEM-TRD tests===
 
 
[[CPP_Test_2020_-_Schedule]]
 
 
# Restricted access on 31st, RADCOM sweep will start at 6 am
 
 
[[Media:CPP_GEM_Test_install_schedule_Aug2020.pdf]]
 
 
=Thursday, August 27=
 
# Last 24 hours:
 
#* Due to Hall C current increase request, accelerator experimented with the optics => MCC recommended a HARP scan, [https://logbooks.jlab.org/entry/3835221 1st scan] and [https://logbooks.jlab.org/entry/3835162 2nd scan]
 
#* Production
 
## [https://logbooks.jlab.org/entry/3835500 Many short trips - beam stable for 5 min and then trips]
 
## We lost 8hrs ie runs 72873 to 72876 cannot be used in analysis
 
# Report/issues:
 
#* [https://logbooks.jlab.org/entry/3835133 HARP scan - fit fails because of the beam trip], [https://logbooks.jlab.org/entry/3835232 corrected by Hovanes]
 
#* CDC HV tripped twice: [https://logbooks.jlab.org/entry/3835005 around 16:00] and [https://logbooks.jlab.org/entry/3835444 around 22:00]
 
#* [https://logbooks.jlab.org/entry/3835444 FDC HV tripped]
 
#* no HV alarms for CDC and FDC but problem visible on [https://halldweb.jlab.org/data_monitoring/Plot_Browser.html?minRunNum=72863&maxRunNum=72878&RunPeriod=RunPeriod-2019-11&Version=rawdata_ver00&Plot=CDC_occupancy&rcdb_query=daq_run%3D%3D%27PHYSICS_DIRC%27%20and%20event_count%20%3E%20500000%20and%20solenoid_current%20%3E%20100%20and%20collimator_diameter%20%21%3D%20%27Blocking%27 online monitoring plots] and [https://logbooks.jlab.org/comment/30243#comment-30243 HydraRun saw it]
 
#* [https://logbooks.jlab.org/comment/30248#comment-30248 Hovanes reported a bug in the communication software which causes the alarm problems]
 
# Pending issues:
 
#* TAGM missing channels due to preamp (Nick, Richard). [https://logbooks.jlab.org/entry/3834294 Update]
 
# Run Plan
 
#* Production
 
#* [https://halldweb.jlab.org/wiki/index.php/CPP_Test_2020_-_Schedule CPP test - task 1 to 4 during Ilya's shift]
 
 
===Discussion on trigger/DAQ tests for the SRC/CT===
 
#Sasha requested 5-6 hours on Sunday to do these tests
 
 
===Discussion on CPP and GEM-TRD tests===
 
 
[[CPP_Test_2020_-_Schedule]]
 
# Restricted or controlled access for 31st depends on if there is 1/2 rack available or not
 
 
[[Media:CPP_GEM_Test_install_schedule_Aug2020.pdf]]
 

Revision as of 12:55, 2 September 2020

<- Back to Run Coordination Meetings:Summer2020

Integrated trigger count

GlueX Statistics Run Sheet


MEDCON 5 restrictions (Bob May email)

  1. adhere to counting room capacity restrictions
  2. maintain 6 ft. separation (briefly passing another person inside 6 ft. while moving about the counting room is inevitable and is OK)
  3. wear masks anytime more than one person present in the counting room
  4. at MEDCON 5 the lab has no cafeteria services because eating "cafeteria style" (eating in common from prepared food) is inconsistent with COVID-19 controls. Staging food in the counting room to share is inconsistent with MEDCON 5 COVID-19 controls.
  5. food and drink consumption - because it requires removing face coverings to consume - should be limited to packaged food and drink brought for personal use that is consumed while maintaining at least 6 ft. from the nearest person and ideally, consumed in a separate room from others.

Thursday, September 3

  1. Last 24 hours:
  2. Report/issues:
  3. Pending issues:
    • TAGM missing channels due to preamp (Nick, Richard). Update
  4. Run plan
    • Ramping up magnet at 10 am
    • Diamond 0/90 PARA
      • 2 hours: focused FCAL trigger in GEM location (FCAL_TRACK_CENT_m9.conf)
      • 8 hours: standard FCAL-BCAL trigger at 150 nA (low energy TAGH turned on)
      • 4 hours: standard FCAL-BCAL trigger at 250 nA (low energy TAGH turned off)
      • 4 hours: standard FCAL-BCAL trigger at 350 nA (low energy TAGH turned off)