(Friday, September 4)
(Friday, September 4)
Line 16: Line 16:
 
# Last 24 hours:
 
# Last 24 hours:
 
#* Data taking for DIRC/GEM/TRD finished at 6:40. (~4h downtime in the yesterday's evening)
 
#* Data taking for DIRC/GEM/TRD finished at 6:40. (~4h downtime in the yesterday's evening)
 +
#* De-installation work in progress
 
# Reports/issues:
 
# Reports/issues:
 
#* [https://logbooks.jlab.org/entry/3840134 monitoring farm is not processing data]
 
#* [https://logbooks.jlab.org/entry/3840134 monitoring farm is not processing data]

Revision as of 06:47, 4 September 2020

<- Back to Run Coordination Meetings:Summer2020

Integrated trigger count

GlueX Statistics Run Sheet


MEDCON 5 restrictions (Bob May email)

  1. adhere to counting room capacity restrictions
  2. maintain 6 ft. separation (briefly passing another person inside 6 ft. while moving about the counting room is inevitable and is OK)
  3. wear masks anytime more than one person present in the counting room
  4. at MEDCON 5 the lab has no cafeteria services because eating "cafeteria style" (eating in common from prepared food) is inconsistent with COVID-19 controls. Staging food in the counting room to share is inconsistent with MEDCON 5 COVID-19 controls.
  5. food and drink consumption - because it requires removing face coverings to consume - should be limited to packaged food and drink brought for personal use that is consumed while maintaining at least 6 ft. from the nearest person and ideally, consumed in a separate room from others.

Friday, September 4

  1. Last 24 hours:
    • Data taking for DIRC/GEM/TRD finished at 6:40. (~4h downtime in the yesterday's evening)
    • De-installation work in progress
  2. Reports/issues:
  3. Run plan
    • foobar

Thursday, September 3

  1. Last 24 hours:
    • -10 am: straight-track data for GEM/TRD
    • Solenoid ramping up during RF recovery, 1352.6 A at 6:40 pm [1].
    • Beam comes back at 9:45 pm. Harp scan.
  2. Reports/issues:
  3. Run plan
    • Continue DIRC commissioning until 6 am tomorrow morning.
    • De-installation work from 6 am (will take 2 - 3 hours)
    • Resume production runs
    • Controlled access to the tagger hall to replace the preamp, should coincide with de-installation work? (Richard, Nick)