Line 79: | Line 79: | ||
* Hall D techs Beamline assembled and pump | * Hall D techs Beamline assembled and pump | ||
* Hall D techs Ramp up the magnet | * Hall D techs Ramp up the magnet | ||
+ | |||
+ | === 2. Prior to beam activities === | ||
+ | |||
+ | * Establish typical tagged photon beam | ||
+ | * Harp scans for the electron Beam (and PS) | ||
+ | * Initial detector check out | ||
+ | * Equalize CCAL gains (calibrate CCAL) | ||
+ | * TAC run | ||
+ | |||
===Loading Liquid Targets=== | ===Loading Liquid Targets=== |
Revision as of 09:51, 27 August 2021
Contents
Tentative Schedule
Activity | Time | Beam Conditions |
---|---|---|
Target change C ladder |
3 shifts | no beam |
Detector and DAQ checkout | 2 shifts | 140 nA |
Luminosity Scan | 1 shift | Varies |
Run with C target |
20 days | 140 nA |
Compton running for density checks | 1 shift | |
Target change to 4He | 5 shifts | |
Compton running for density checks | 1-2 shift | |
Run with 4He | 10 days | 140 nA |
Empty Cell Run | 1 shift | 140 nA |
Target change to D | 3 shifts | |
Run D | 8 days | 140 nA |
Target change to Cu | 5 shifts | |
Run with Cu | 10 days | 140 nA |
Detailed Activities
1. Prior to beam activities
Estimated time (3 -4 Shifts: 1 Day)
- With Radcon support, Hall D techs uncable and remove start counter from cryostat
- With Radcon support, Target Group secures target gas, inerts the target piping, and bleeds vacuum chamber to atmospheric pressure
- With Radcon support, Target Group removes foam portion of cryostat
- With Radcon support, Target Group removes foam portion of cryostat
- With Radcon support, Target Group removes superinsulation around target cell
- With Radcon support, Target Group removes target cell
- With Radcon support, Target Group mounts Carbon ladder in place of the gas cell
- With Radcon support, Target Group, Foam portion of cryostat is put back in place, vacuum pumps on
- With Radcon support, Hall D techs Start counter put back in place, cables attached
- With Radcon support, Hall D techs Target inserted into solenoid
- Survey adjusts position in solenoid
- Hall D techs Beamline assembled and pump
- Hall D techs Ramp up the magnet
2. Prior to beam activities
- Establish typical tagged photon beam
- Harp scans for the electron Beam (and PS)
- Initial detector check out
- Equalize CCAL gains (calibrate CCAL)
- TAC run
Loading Liquid Targets
Contact | Details | |
---|---|---|
Disassemble beam pipe Retract target Remove ST Remove Gluex Cell |
||
Mount target cell Mount heat shield |
||
Survey | ||
Attach vacuum snout Attach ST Target in place Assemble beam pipe Pump vacuum in the target ladder |
||
Ramp Magnet up |
Loading Solid Targets
Contact | Details | |
---|---|---|
Disassemble beam pipe Retract target Remove ST Remove Gluex Cell |
||
Mount C foil ladder | ||
Survey | ||
Attach vacuum snout Attach ST Target in place Assemble beam pipe Pump vacuum in the target ladder |
||
Ramp Magnet up |