SRC/CT Run Plan
From GlueXWiki
Revision as of 09:48, 8 July 2021 by Ssanties (Talk | contribs) (Created page with "==Tentative Schedule== {| class="wikitable" |- style="font-weight:bold;" ! Activity ! Time ! Beam Conditions<br /> |- | Target change C ladder<br /><br /> | 3 shifts | no be...")
Contents
Tentative Schedule
Activity | Time | Beam Conditions |
---|---|---|
Target change C ladder |
3 shifts | no beam |
Detector and DAQ checkout | 2 shifts | 140 nA |
Luminosity Scan | 1 shift | Varies |
Run with C target |
20 days | 140 nA |
Compton running for density checks | 1 shift | |
Target change to 4He | 5 shifts | |
Compton running for density checks | 1-2 shift | |
Run with 4He | 10 days | 140 nA |
Empty Cell Run | 1 shift | 140 nA |
Target change to D | 3 shifts | |
Run D | 8 days | 140 nA |
Target change to Cu | 5 shifts | |
Run with Cu | 10 days | 140 nA |
Detailed Activities
Loading Liquid Targets
Contact | Details | |
---|---|---|
Disassemble beam pipe Retract target Remove ST Remove Gluex Cell |
||
Mount target cell Mount heat shield |
||
Survey | ||
Attach vacuum snout Attach ST Target in place Assemble beam pipe Pump vacuum in the target ladder |
||
Ramp Magnet up |
Loading Solid Targets
Contact | Details | |
---|---|---|
Disassemble beam pipe Retract target Remove ST Remove Gluex Cell |
||
Mount C foil ladder | ||
Survey | ||
Attach vacuum snout Attach ST Target in place Assemble beam pipe Pump vacuum in the target ladder |
||
Ramp Magnet up |