Line 12: | Line 12: | ||
*** Lead absorbers - drawings in review | *** Lead absorbers - drawings in review | ||
*** assembly components - drawings in review | *** assembly components - drawings in review | ||
− | ** Stand All parts here - to be assembled in the TEDF High bay] | + | ** Stand All parts here - to be assembled in the TEDF High bay [[image:cpp_stand_1.jpg|thumb]] [[image:cpp_stand_2.jpg|thumb]] [[image:cpp_stand_3.jpg|thumb]] |
** Steel - all received [[image:cpp_steel_3.jpg|thumb]] | ** Steel - all received [[image:cpp_steel_3.jpg|thumb]] | ||
** Fcal platform mods | ** Fcal platform mods |
Revision as of 13:37, 9 September 2021
Meeting Time and Place
Thursday August 26, 2021, 3:00pm Bluejeans https://bluejeans.com/465620466
- Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S, Beni, Simon, Mark I
Agenda
- Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/August_26,_2021_CPP_Design_Meeting
- Testing status - Beni
- Design/Fab/Procurement status
- Installation/assy 3D Model and dwgs
- Lead absorbers - drawings in review
- assembly components - drawings in review
- Stand All parts here - to be assembled in the TEDF High bay
- Steel - all received
- Fcal platform mods
- Cutouts complete
- Floor Rails installed and aligned
- Installation/assy 3D Model and dwgs
- Things to work out
- Gas system, manifold/bubblers (Beni has some)
- Complete structural analysis - approved by Tom Renzo - need to release into system
- Develop Detailed installation plan
- Develop Design/operational/Maintenance Requirements
- Modified US vacuum system
- Solid target installation
- Installation drawing including Microscope move
- CPP Detector operations in Hall D OSP
- Possible use of nitrogen flow for cooling electronics in Faraday cage