Meeting Time and Place

Thursday Sept 2, 2010 at 8:15am At Jefferson Lab, the meeting will be held in room ARC 428

Agenda

  • ESH&Q minute (Ladder Safety)
  • Hurricane preparedness
  • Announcements (
  • Look at platform adjustments (Rich)
  • Lehman review preparations *
  • Solenoid Test Status *
  • Civil construction Status *
  • Tagger magnet status

Outstanding Action Items

  • Determine new positions of cryo transfer line supports and feedback to civil (Jim/Tim)* Under work - needs to be settled within the next few weeks
  • Correct platform height and location for new expansion can (make sure there is room to stab u-tubes)(Jim/Rich)* Some work done, will review next week
  • Need to develop a leak check and assy plan for cryo lines (Jim/Tom) in work
  • Look at getting traps/strainers for power supply LCW (Josh F.)
  • Identify PLC programmer to take over for Mark Wissman (Tim)
  • Need to put PR out for FDC techs (Tim)
  • Set up for Dave to give presentation on FDC procedures at a later meeting (Tim)
  • Tom to come up with a list of equipment needed.

Discussions

    • In attendance W. Crahen, G. Biallas, J. Fochtman, T. Carstens, C. Hutton, V. Razmyslovich, J. Lagner, F. Martin, R. Getz, J. Foyles, M. Stevens, R. Bunton, G. Humble, C. Heck, D. Butler, K. Sullivan, Josh Ballard, W. Sachleben, Tim Whitlatch


Action Items