1. FCAL blocks - inspect one crate- complete
+
** FCAL blocks - inspect one crate- complete
2. Trial assembly of BCAL wedges - lifting and support tooling being designed
+
** Trial assembly of BCAL wedges - lifting and support tooling being designed
3. Test PS magnet - elect. and water - Josh Ballard writing requirements
+
** Test PS magnet - elect. and water - Josh Ballard writing requirements
4. Split PS magnet - after testing
+
** Split PS magnet - after testing
5. Modify PS magnet - when hardware available
+
** Modify PS magnet - when hardware available
6. Weld perm mag chambers - 2 ea - slava has dwgs
+
** Weld perm mag chambers - 2 ea - slava has dwgs
7. Weld DW magnet beam tube - Slava to define
+
** Weld DW magnet beam tube - Slava to define
8. Install perm and DW mags in collimator cave
+
** Install perm and DW mags in collimator cave
9. Assemble and test BCAL readout prototype -complete
+
** Assemble and test BCAL readout prototype -complete
10. Drill/tap solenoid yokes in laydown area - fillers to be available in August
+
** Drill/tap solenoid yokes in laydown area - fillers to be available in August
11. Help Beni with gass system assy/test in EEL 126
+
** Help Beni with gass system assy/test in EEL 126
12. Fabricate cable install mock up - John Conger currently designing
+
** Fabricate cable install mock up - John Conger currently designing
13. Cover trenches in Hall with plywood or cones for safety - complete
+
** Cover trenches in Hall with plywood or cones for safety - complete
14. Install dehumidifiers in Hall D - complete
+
** Install dehumidifiers in Hall D - complete
15. Camera mount in Hall
+
** Camera mount in Hall
16. BCAL light guide gluing tests
+
** BCAL light guide gluing tests
17. Weld tests on solenoid baffles
+
** Weld tests on solenoid baffles
  
 
== Open Action Items==
 
== Open Action Items==

Latest revision as of 08:39, 2 September 2011

Meeting Time and Place

Friday Sept 2, 2011 at 9am At Jefferson Lab, the meeting will be held in room ARC 231

Agenda

  • ESH&Q minute -
  • Announcements -
    • training -
    • Manpower -
  • Solenoid Test Status *
  • FDC construction update -
  • Upcoming work
    • FCAL blocks - inspect one crate- complete
    • Trial assembly of BCAL wedges - lifting and support tooling being designed
    • Test PS magnet - elect. and water - Josh Ballard writing requirements
    • Split PS magnet - after testing
    • Modify PS magnet - when hardware available
    • Weld perm mag chambers - 2 ea - slava has dwgs
    • Weld DW magnet beam tube - Slava to define
    • Install perm and DW mags in collimator cave
    • Assemble and test BCAL readout prototype -complete
    • Drill/tap solenoid yokes in laydown area - fillers to be available in August
    • Help Beni with gass system assy/test in EEL 126
    • Fabricate cable install mock up - John Conger currently designing
    • Cover trenches in Hall with plywood or cones for safety - complete
    • Install dehumidifiers in Hall D - complete
    • Camera mount in Hall
    • BCAL light guide gluing tests
    • Weld tests on solenoid baffles

Open Action Items

New Action Items

  • OSP for ceiling plates

Discussions

    • In attendance Tim Whitlatch, S. Speigel, G. Humble, , B. Bunton, M. Stevens, S. Speigel, J. Thoamason, J. Foyles, C. Heck, T. Mann, M. Beizer, A. Johnson, T. Carstens