Meeting Information

GlueX DIRC Meeting
Monday September 24, 2018
1:00 pm, EDT
JLab room A110

Connection Using Bluejeans

  1. To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 846453895.
  2. To join via a Web Browser, go to the page [1] https://bluejeans.com/846453895 .
  3. To join via phone, use one of the following numbers and the Conference ID: 846453895
    • US or Canada: +1 408 740 7256 or
    • US or Canada: +1 888 240 2560
  4. More information on connecting to bluejeans is available.

Agenda

  1. Announcements
    • Collaboration meeting this week
  2. Optical box
    • Fabrication status update (Ernie and Jason)
      • Mirror box completion and delivery
      • Dark box enclosure (Jason)
      • Quartz window (with modified flange) (Ernie)
    • Updated installation schedule: [2]
    • Testing in ESB
      • Mirror box laser alignment (Bill)
  3. DAQ integration
    • 2 modules with internal pulser readout (Logbook) and successfully tased
  4. Slow controls
    • Initial versions of voltage GUIs in place, scalers will follow.
  5. Software/simulations
    • Software overview and tasks (All)
    • Finalizing DIRC "as-built" geometry: support frames, bar box internals, etc. (Yunjie)
      • Individual bar dimensions implemented in HDDS
      • XML parser written to make alignment adjustments: account for survey, rotations of optical/bar boxes, etc.
    • Time-based studies (Maria)
  6. Addressing ERR review recommendations
    • Recommendations pertaining to Fall 2018 DIRC commissioning should be addressed before October installation (required for new beam time request)