(Created page with "== Attendees == George B., David B., Mark S., Yi Q. == Minutes == Task List # PXI ground jumpers: installed # LHe level probe: Scot received wiring diagram from cryo group, wi...")
 
(Minutes)
 
Line 9: Line 9:
 
# LHe level probe: Scot received wiring diagram from cryo group, will verify the connection
 
# LHe level probe: Scot received wiring diagram from cryo group, will verify the connection
 
# HW QD balance resistor: file still missing, will find more places including a local machine
 
# HW QD balance resistor: file still missing, will find more places including a local machine
 +
# Ground Fault Detector signal to PXI: connected
 
# Power supply spare: Mark will help look into it
 
# Power supply spare: Mark will help look into it
 
# Control of Solenoid from Counting House: HMI & EPICS, start thinking, will breakdown sub-items later
 
# Control of Solenoid from Counting House: HMI & EPICS, start thinking, will breakdown sub-items later

Latest revision as of 11:52, 11 February 2014

Attendees

George B., David B., Mark S., Yi Q.

Minutes

Task List

  1. PXI ground jumpers: installed
  2. LHe level probe: Scot received wiring diagram from cryo group, will verify the connection
  3. HW QD balance resistor: file still missing, will find more places including a local machine
  4. Ground Fault Detector signal to PXI: connected
  5. Power supply spare: Mark will help look into it
  6. Control of Solenoid from Counting House: HMI & EPICS, start thinking, will breakdown sub-items later
  7. Short sample tests at Twenty University: George will push it
  8. Incorporate PLC into Operator alarm system: Yi will look into it
  9. Auto log entries: start thinking, may proceed with event-triggered entries