== Commissioning Tasks and Milestones == | == Commissioning Tasks and Milestones == | ||
− | |||
* Develop scripts for LED timing offset calibration (Nov 1) --- Yunjie | * Develop scripts for LED timing offset calibration (Nov 1) --- Yunjie | ||
* Develop EVIO parser and Translation Table (Nov 1) --- Bill/Justin | * Develop EVIO parser and Translation Table (Nov 1) --- Bill/Justin | ||
Line 21: | Line 20: | ||
== Commissioning Timeline, Tasks and Milestones == | == Commissioning Timeline, Tasks and Milestones == | ||
− | * <strike>'''July 16-30:''' Integration of DIRC crate with DAQ and initial test of readout with standalone MAPMT module (Ben, Sergey, Sasha)< | + | * <strike>'''July 16-30:''' Integration of DIRC crate with DAQ and initial test of readout with standalone MAPMT module (Ben, Sergey, Sasha)</strike> |
* '''August-October''' | * '''August-October''' | ||
− | ** <strike>Implementation of DAQ decoder for SSP data format in sim-recon to create low level hit objects (David)< | + | ** <strike>Implementation of DAQ decoder for SSP data format in sim-recon to create low level hit objects (David)</strike> |
+ | ** Calibration document with expected tables for CCDB (Oct 22) --- Justin | ||
** Implementation of Translation Table in CCDB to orient (FPGA, channel ID) mapping from readout into physical pixel coordinates (X, Y) position along readout window (Nov 1) --- David, Justin, Bill | ** Implementation of Translation Table in CCDB to orient (FPGA, channel ID) mapping from readout into physical pixel coordinates (X, Y) position along readout window (Nov 1) --- David, Justin, Bill | ||
− | ** Online and offline monitoring plugins to monitor occupancies and timing distributions | + | ** Online and offline monitoring plugins to monitor occupancies and timing distributions (Nov 1) --- TBD |
*** LED occupancy and timing calibration (Nov 1) --- Yunjie | *** LED occupancy and timing calibration (Nov 1) --- Yunjie | ||
*** Physics trigger occupancies and timing - possibly use TOF/FCAL as filter for tracks in different regions (Nov 1) --- TBD | *** Physics trigger occupancies and timing - possibly use TOF/FCAL as filter for tracks in different regions (Nov 1) --- TBD |
Revision as of 12:36, 24 September 2018
Contents
Commissioning Goals
- Integrate DIRC readout with general Hall D DAQ and online/offline monitoring
- Confirm cabling through HV/mask checks with LED system
- Calibrate per-pixel timing offset of MAPMTs using LED system
- Determine geometric alignment parameters (position and angle offsets) for optical components
- Implement reconstruction algorithm and compare data/MC: # detected photons, Cherenkov angle resolution
Commissioning Observables
- "Ring" images for tracks with fixed kinematics (binned in position space over bars) overlaid on MC distributions
- Per-pixel timing and Cherenkov angle differences (measured - LUT expected) to confirm geometry
- Number of detected photons/track
- Single photon resolution (SPR) per pixel
Commissioning Tasks and Milestones
- Develop scripts for LED timing offset calibration (Nov 1) --- Yunjie
- Develop EVIO parser and Translation Table (Nov 1) --- Bill/Justin
Commissioning Timeline, Tasks and Milestones
-
July 16-30: Integration of DIRC crate with DAQ and initial test of readout with standalone MAPMT module (Ben, Sergey, Sasha) - August-October
-
Implementation of DAQ decoder for SSP data format in sim-recon to create low level hit objects (David) - Calibration document with expected tables for CCDB (Oct 22) --- Justin
- Implementation of Translation Table in CCDB to orient (FPGA, channel ID) mapping from readout into physical pixel coordinates (X, Y) position along readout window (Nov 1) --- David, Justin, Bill
- Online and offline monitoring plugins to monitor occupancies and timing distributions (Nov 1) --- TBD
- LED occupancy and timing calibration (Nov 1) --- Yunjie
- Physics trigger occupancies and timing - possibly use TOF/FCAL as filter for tracks in different regions (Nov 1) --- TBD
- Include DIRC hit patterns in event display --- TBD
-
- October 29 - November 18 (3-week install period):
- Verify cabling and translation table with LED data (1 week after install) --- TBD
- Design unique patterns of HV and channel masks
- Collect ~100k events in each configuration to verify mapping
- HV and threshold scans with LED data (2 weeks after install) --- TBD
- Duplicate scans of HV and thresholds as used in laser test setup (see below)
- Determine initial HV and threshold settings for LED and beam data
- Initial time offset calibrations with LED data (3 weeks after install) --- Yunjie
- Verify cabling and translation table with LED data (1 week after install) --- TBD
- November 19 - December 19 (commissioning with beam):
- Complete integration with DAQ under low-intensity beam conditions: (1 week)
- Evaluate scaler rates and distributions relative to MC predictions
- Mask any noisy channels for production data
- Determine what global parameters can be optimized (beam current, bar box position, etc.) can be optimized
- Production data taking with all sub-detectors in nominal condition (2 weeks, production overnight)
- FCAL-BCAL production physics trigger with interleaved DIRC LED and random triggers
- Collect sufficient statistics for optical alignment with identified ρ and φ, as well as more
- Intensity scans ** (1 week, production overnight)
- Complete integration with DAQ under low-intensity beam conditions: (1 week)
- Evaluate rate dependence and backgrounds for both high and low luminosity
- Scans of fixed amorphous radiator and varied current from 50 - 300 nA
Datasets to acquire with integrated DAQ
HV and threshold scans
- Similar set of HV, MAROC gain, and threshold settings as laser setup for comparison with final implementation
- Validate MAPMT characterization with both LED calibration and beam data