(Commissioning Timeline)
(Commissioning Timeline)
Line 20: Line 20:
 
== Commissioning Timeline ==
 
== Commissioning Timeline ==
 
* '''July 16-30:''' Integration of DIRC crate with DAQ and initial test of readout with standalone MAPMT module (Ben, Sergey, Sasha)
 
* '''July 16-30:''' Integration of DIRC crate with DAQ and initial test of readout with standalone MAPMT module (Ben, Sergey, Sasha)
* '''August'''  
+
* '''August-October'''  
 
** Implementation of DAQ decoder for SSP data format in sim-recon to create low level hit objects (David)
 
** Implementation of DAQ decoder for SSP data format in sim-recon to create low level hit objects (David)
 
** Implementation of Translation Table in CCDB to orient (FPGA, channel ID) mapping from readout into physical pixel coordinates (X, Y) position along readout window (David, Justin, Bill)
 
** Implementation of Translation Table in CCDB to orient (FPGA, channel ID) mapping from readout into physical pixel coordinates (X, Y) position along readout window (David, Justin, Bill)

Revision as of 12:25, 20 August 2018


Commissioning Goals

  • Integrate DIRC readout with general Hall D DAQ and online/offline monitoring
  • Calibrate per-pixel timing offset of MAPMTs using LED system
  • Determine geometric alignment parameters (position and angle offsets) for optical components
  • Implement reconstruction algorithm and compare data/MC: # detected photons, Cherenkov angle resolution

Commissioning Observables

  • "Ring" images for tracks with fixed kinematics
  • Number of detected photons/track
  • Timing difference between measured - expected
  • Single photon resolution (SPR) per pixel

Commissioning Tasks and Milestones

  • Develop EVIO parser and Translation Table
  • Develop scripts for LED timing offset calibration
  • Calibration document with expected tables for CCDB

Commissioning Timeline

  • July 16-30: Integration of DIRC crate with DAQ and initial test of readout with standalone MAPMT module (Ben, Sergey, Sasha)
  • August-October
    • Implementation of DAQ decoder for SSP data format in sim-recon to create low level hit objects (David)
    • Implementation of Translation Table in CCDB to orient (FPGA, channel ID) mapping from readout into physical pixel coordinates (X, Y) position along readout window (David, Justin, Bill)
    • Online and offline monitoring plugins to monitor occupancies and timing distributions (TBD)
      • LED occupancy and timing calibration (Yunjie)
      • Physics trigger occupancies and timing - possibly use TOF/FCAL as filter for tracks in different regions (TBD)
    • Include DIRC hit patterns in event display?
  • October 29 - November 18 (3-week install period):
    • Verify cabling and translation table with LED data (unique patterns of HV on/off)
    • Initial time offset calibrations with LED data
    • HV and threshold scans with LED data
  • November 19 - December 19 (commissioning with beam):
    • TBD

Datasets to acquire with integrated DAQ

HV and threshold scans

  • Similar set of HV, MAROC gain, and threshold settings as laser setup for comparison with final implementation
  • Validate MAPMT characterization with both LED calibration and beam data

Intensity scans

  • Evaluate rate dependence and backgrounds for both high and low luminosity
  • Scans of fixed amorphous radiator and varied current from 50 - 300 nA

Simulation studies for commissioning

Requirements

  • Final "as built" geometry in CCDB with appropriate run number
  • Define JANA calibration variation for CCDB specific to DIRC(?)
  • LUT algorithm implemented as factory in DIRC sim-recon library

Data Samples

  • bggen sample (1M events) for comparison of rates and occupancies with data
  • single track pion and kaon samples in kinematic bins for comparison with data