Draft Run Plan for the PrimEx-D Run for first few weeks

(Updated: 01/10/2019)

Overview

The goal of the experiment: extract the η rad. decay width with as high accuracy as possible.

How: from the measured absolute diff. cross sections.

The method:

  1. measure the Compton diff. cross section on 5% Be target;
  2. compare with the known theoretical cross section and extract the so-called “setup normalization constant-Be” (ideally it should be “1”, this number will be sensitive to photon flux and efficiencies of CCAL and FCAL);
  3. measure the same Compton diff. cross section on 4He target;
  4. compare with theory prediction obtained with estimated 4He target density and with the “setup normalization constant-Be”. This new number will be used to normalize our dN(η)/dθ to get the cross sections in μb/Sr.

Run Plan

  1. With empty target:
    • Remove the LH2target cell (if ST needs to come out then remove it also). day shift, 7am - ~4pm
    • Checkout and calibration of CCAL 2 shifts ~4pm – 7am
  1. With Be target:
    • Install Be target, ST possibly in w/o cabling and survey. Day shift, 7am – ~4 pm
    • If Be-target is ready, run Compton ~5 shifts ~4pm – 7am
  1. With 4He target:
    • Work on target, remove Be (if needed remove ST) day shift, 7am – ~4 pm
    • If 4He target is not ready, run “Be empty” target (ST is back) 2 shifts, ~4pm – 7 am
    • Work on target install 4He, ST cabling day shift, 7am - ~4pm
    • Setup checkout with beam 2 shifts, ~4pm – 7am
    • Continue work on 4He, survey day shift, 7am - ~4pm
    • If LHe4 still empty, run “4He empty” 2 shifts, ~4pm – 7am
    • If “empty” is finished, fill 4He target and run LHe4 Compton
    • Prepare the setup and run for η-Primakokf ~4pm – April
    • Keep analyzing data