Summer 2020 DIRC Commissioning

From GlueXWiki
Revision as of 08:03, 1 September 2020 by Jrsteven (Talk | contribs)

Jump to: navigation, search


== Detector location and plane labeling

Lubomir's presentation

Calibration datasets

Summary page for Summer 2020 TRD/GEM Commissioning lists the relevant run ranges for the datasets collected below

Straight-track data

  • For alignment of the GEM/TRD we need to acquire production samples with the magnetic field off
  • Straight-track sample at the beam-center TRD positions with the full GEM readout for tracking and alignment studies
    • Standard GlueX no-field measurements with 50nA on 10^-4 amorphous radiator
    • 2 hours: focused FCAL trigger in GEM location to verify TRD/GEM signals (raw mode)
    • 8 hours: standard FCAL-BCAL trigger for alignment data

Full GEM readout: tracking mode

  • With the aligned GEM/TRD collect data for track extrapolation validation and multi-plane tracking directly upstream of DIRC
  • Full solenoid field sample at the beam-center TRD positions with the full GEM readout for tracking and alignment studies
    • Standard GlueX running conditions at 150nA, 250 nA and 350nA
    • 2 hours: focused FCAL trigger in GEM location to verify TRD/GEM signals (raw mode)
    • 8 hours: standard FCAL-BCAL trigger for alignment data at 150 nA (low energy TAGH turned on)
    • 4 hours: standard FCAL-BCAL trigger for alignment data at 250 nA (low energy TAGH turned off)
    • 4 hours: standard FCAL-BCAL trigger for alignment data at 350 nA (low energy TAGH turned off)

Full GEM readout: TRD mode

  • For TRD pion rejection performance acquire production samples with the TRD in "cluster counting" mode with all the GEM packages read out.
  • Operate TRDs with two different gasses using raw mode (Lubomir and Sergey required)
    • 4 hours: standard FCAL-BCAL trigger