Meeting Information
GlueX DIRC Review Meeting October, 14 2015
Review Committee:
- Thomas K. Hemmick (Chair) Stony Brook University
- Clara Matteuzzi INFN Milano Bicocca
- Marco Contalbrigo INFN Ferrara
- Jerry Va'vra SLAC
- Allison Lung Jefferson Lab
- David Abbott Jefferson Lab
- Javier Gomez Jefferson Lab
- Tim Whitlatch Jefferson Lab
DOE Observers:
- Gulshan Rai DOE/SC
- Jehanne Gillo DOE/SC
- Elizabeth Bartosz DOE/SC
Preliminary Agenda
- 8:00 - 8:30 Executive Session
- 8:30 - 9:30 (40 + 20) Introduction and Project Overview (Curtis)
- Meson spectroscopy introduction with focus on strange final states
- Kaon ID limitations with baseline GlueX and improvements with DIRC
- Overview of GlueX run plan
- Review of BaBar design and SLAC FDIRC prototype
- General overview of design, referring to later talks for specifics
- Summarize requirements for RICH MaPMT readout and show they're well matched to the DIRC (including DAQ/Trigger)
- Evaluation of design based on John's simulation
- 9:30 - 10:15 (30 + 15) Focusing Box Prototype Studies (Mike)
- Overview of prototype design
- John's test setup at Bates and mirror characterization
- Plans for full scale box design
- 10:15 - 10:45 Break
- 10:45 - 11:30 (30 + 15) Mechanical Design, Integration and Transport (Matt)
- Support structure design and integration with forward carriage
- Reasoning for horizontal (instead of vertical) design
- Shipping crate design and tests with accelerometers at IU on mock bar box
- 11:30 - 12:30 (40 + 20) Project Management, Cost, and Schedule (Justin)
- Similar to Patrizia's talk for CLAS12 review: management structure, contingencies, cost/schedule in gantt chart, etc.
- 12:30 - 1:30 Lunch (Executive Session)
- 1:30 - 4:00 Executive Session
- 4:00 Closeout
TDR preparation schedule
- October 14: External review at JLab
- October 7: Dry runs of talks at JLab
- September 30: Submit final TDR to external committee
- September 23: Submit draft TDR to collaboration for review
- September 7: Receive feedback from internal committee's review of TDR
- August 28: Submit draft TDR to internal committee for review
- August 14: Complete drafts of all TDR sections
- Early July: First draft of all TDR sections
- Early June: Complete outline of TDR sections
Documents
- SVN repository for TDR
- Eventually will link to relevant document(s) on DocDB
- LHCb Paper on Multianode PMT arXiv.
- Talks for review in DocDB
- etc.