Drift Chamber Alignment

From Hall D Ops Wiki
Jump to: navigation, search

Drift Chamber Alignment

  1. Goal: Collect data with no or low field.
  2. Responsibility: HallD
  • Expected Schedule: See start dates in the run coordination meeting pages here and the general schedule here: Duration of the Drift Chamber Alignment : 4 days
  1. Conditions:
    • Tagger hall equipment in place and operating.
    • Beam 50nA CW
    • Radiator is 0.2 - 1.0 10-4 RL, depending on the FDC and trigger rates.
    • Collimator hole is 5 mm.
    • Solenoid 0-300A depending on backgrounds.
    • GlueX detectors are on.
    • Thin commissioning targets at various positions.
  2. Activities
    • If time permits, collect data with target in several positions.

Back to main Fall14 commissioning page