Difference between revisions of "Tune Electron Beam"
From Hall D Ops Wiki
(→Tune Electron Beam (Time estimate: 15 days)) |
|||
(23 intermediate revisions by 3 users not shown) | |||
Line 1: | Line 1: | ||
− | |||
− | |||
− | |||
* Goal: provide a clean electron beam through the center of the beam aperture to the beam dump in the tagger hall with acceptable radiation levels. | * Goal: provide a clean electron beam through the center of the beam aperture to the beam dump in the tagger hall with acceptable radiation levels. | ||
* Priority: High | * Priority: High | ||
* [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/14423 Link to the accelerator test plan for electron beam commissioning (ATLIS)] | * [http://opsweb.acc.jlab.org/CSUEApps/atlis/task/14423 Link to the accelerator test plan for electron beam commissioning (ATLIS)] | ||
* Expected duration: | * Expected duration: | ||
− | # | + | # 4 days: Tune beam to Hall D line dumplette (Tagger Hall can remain open). |
− | # | + | # 3 days: Tune beam to Tagger Hall D (Tagger Hall and Hall D must be closed). |
* Prerequisites: | * Prerequisites: | ||
− | # Tagger microscope (TAGM) and all the crates with electronics | + | # Tagger microscope (TAGM) and all the crates with electronics removed from Hall D. <span style="font-size:21px">☑</span> |
− | + | # Goniometer in the beam-open position. The goniometer will not be used during the 2014 run. <span style="font-size:21px">☑</span> | |
− | # Goniometer in the beam-open position. The goniometer will not be used during the 2014 run | + | # Amorphous radiator ladder equipped and operational <span style="font-size:21px">☑</span> |
− | # Amorphous radiator ladder equipped | + | #* Responsibility: Hovanes Egiyan. |
− | #* Responsibility: Hovanes Egiyan. | + | # Beam lines under vacuum <span style="font-size:21px">☑</span> |
− | + | # Tagger magnet operational <span style="font-size:21px">☑</span> | |
− | # Beam lines under vacuum | + | #* Responsibility: MCC |
− | # Tagger magnet operational | + | # Shielding walls installed <span style="font-size:21px">☑</span> |
− | # Shielding walls installed | + | # Radiation monitors installed and operational <span style="font-size:21px">☑</span> |
− | # Radiation monitors installed and operational | + | #* Responsibility: Alexandre Deur (CARMS)/Hovanes Egyian (halo counters) |
− | # | + | #* [https://hdops.jlab.org/wiki/index.php/How_to_read_temporary_CARMS Procedure to monitor CARMs] |
− | # Profiler | + | # Upstream Profiler installed in front of the collimator <span style="font-size:21px">☑</span> |
+ | # Downstream Profiler installed in front of photon beam dump <span style="font-size:21px">☑</span> | ||
* Conditions: | * Conditions: | ||
# Pulsed beam [https://halldweb1.jlab.org/wiki/index.php/Tune_mode pulsed beam] 4-10 µA (average 60-150 nA) for the beam tune | # Pulsed beam [https://halldweb1.jlab.org/wiki/index.php/Tune_mode pulsed beam] 4-10 µA (average 60-150 nA) for the beam tune | ||
# CW beam 50-100 nA at the final stage of the procedure | # CW beam 50-100 nA at the final stage of the procedure | ||
− | # No radiator | + | # Primary collimator block in the position between two holes, shielding the central area of the beam pipe <span style="font-size:21px">☑</span>. Secondary collimator removed. <span style="font-size:21px">☑</span> |
− | # | + | #* Responsibility: Hovanes Egiyan. |
− | # | + | #* [[Beam_Line_Detectors_Shift#Move_Collimator | Procedure for moving Primary Collimator]] |
− | # No shift workers in Hall D | + | # Vacuum window covers removed (7 window covers) <span style="font-size:21px">☑</span> |
+ | # No radiator inserted. <span style="font-size:21px">☑</span> | ||
+ | #* Responsibility: Hovanes Egiyan. | ||
+ | #* [[Tagging_Spectrometer_Shift#Move_Amorphous_Radiator | Procedure for inserting/removing amorphous radiators]] | ||
+ | # No shift workers in Hall D except if needed. RC and/or other Hall D personnel follows the beam tuning procedure at the MCC. | ||
− | + | [https://hdops.jlab.org/wiki/index.php/Fall_2014_Commissioning_Plan Back to main Fall14 commissioning page] | |
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + | ||
− | + |
Latest revision as of 09:58, 22 October 2014
- Goal: provide a clean electron beam through the center of the beam aperture to the beam dump in the tagger hall with acceptable radiation levels.
- Priority: High
- Link to the accelerator test plan for electron beam commissioning (ATLIS)
- Expected duration:
- 4 days: Tune beam to Hall D line dumplette (Tagger Hall can remain open).
- 3 days: Tune beam to Tagger Hall D (Tagger Hall and Hall D must be closed).
- Prerequisites:
- Tagger microscope (TAGM) and all the crates with electronics removed from Hall D. ☑
- Goniometer in the beam-open position. The goniometer will not be used during the 2014 run. ☑
- Amorphous radiator ladder equipped and operational ☑
- Responsibility: Hovanes Egiyan.
- Beam lines under vacuum ☑
- Tagger magnet operational ☑
- Responsibility: MCC
- Shielding walls installed ☑
- Radiation monitors installed and operational ☑
- Responsibility: Alexandre Deur (CARMS)/Hovanes Egyian (halo counters)
- Procedure to monitor CARMs
- Upstream Profiler installed in front of the collimator ☑
- Downstream Profiler installed in front of photon beam dump ☑
- Conditions:
- Pulsed beam pulsed beam 4-10 µA (average 60-150 nA) for the beam tune
- CW beam 50-100 nA at the final stage of the procedure
- Primary collimator block in the position between two holes, shielding the central area of the beam pipe ☑. Secondary collimator removed. ☑
- Responsibility: Hovanes Egiyan.
- Procedure for moving Primary Collimator
- Vacuum window covers removed (7 window covers) ☑
- No radiator inserted. ☑
- Responsibility: Hovanes Egiyan.
- Procedure for inserting/removing amorphous radiators
- No shift workers in Hall D except if needed. RC and/or other Hall D personnel follows the beam tuning procedure at the MCC.